J Infratech Limited (CIN U70109HR2019PLC083157) has filed a Draft Red Herring Prospectus with SEBI for an IPO comprising a fresh issue of ₹600 Cr and an offer for sale of 1 Cr shares. In FY26 it reported revenue of ₹1,722 Cr (+22.0% on FY25) and a net profit of ₹247 Cr. Promoters hold 97.7% before the IPO. Our fact-check of its claims found no medium or high concerns across 37 claims checked.
Read from public SEBI filings; last updated . Not investment advice.
Key signals
Read from the filing. Signals summarise it; they are not a recommendation or investment advice.
None serious37 claims checked: 0 high, 0 medium concern.
How we rate these
Valuation: P/E at the top of the band: up to 25x good, up to 40x watch, above that concern.
Growth: Sales growth per year: 20% or more good, 8% or more watch, below that concern.
Profitability: Net profit margin: 10% or more good, 4% or more watch, below that concern. The trend note compares operating margin with the year before (1.5 points either way).
Debt: Borrowings / net worth: up to 0.5x good, up to 1.5x watch, above that concern.
Profit into cash: Cash from operations as a share of net profit: 80% or more good, 40% or more watch, below that (or negative) concern.
One-off income: Other and one-off income as a share of pre-tax profit: up to 10% good, up to 30% watch, above that concern. Any one-off item management itself describes moves "good" to "watch".
Where the money goes: Offer for sale as a share of the whole issue: under 40% good, under 75% watch, above that concern. In an offer for sale the money goes to the selling shareholders, not the company.
Red flags: Fact-check results: any high-concern finding is concern, any medium is watch, otherwise good.
Rules are rules of thumb, not a verdict: a fast-growing business can reasonably carry a higher P/E, and some sectors run on debt.
The IPO
What J Infratech Limited is offering, at what price, and who owns it today. Read from the DRHP; anything the company hasn't fixed yet shows as pending.
Draft under SEBI review
Price band and dates are announced only once the RHP is filed.
Pre-payment or re-payment, in full or in part, of all or a portion of certain outstanding borrowings availed by our Company
50
8.3%
General corporate
General corporate purposes
Not fixed yet
–
Amounts marked “not fixed yet” are left blank in the draft and are set once the price is decided. The offer-for-sale portion is not shown here: that money goes to the selling shareholders, not the company. Source: page 123
Who owns it
Promoters hold before the IPO
97.7%
Promoters 97.7%Promoter group 2.3%
Holder
Shares
% before IPO
Hari NiwasPromoter
5.97 Cr
51.0%
TrustPromoter
4 Cr
34.2%
Mohit JanduPromoter
59.47 lakh
5.1%
Kuldeep KumarPromoter
59.47 lakh
5.1%
SavitriPromoter
26.96 lakh
2.3%
PriyaPromoter group
13.56 lakh
1.2%
MonikaPromoter group
13.56 lakh
1.2%
Virender SinghPromoter group
20,000
0.0%
Valuation
Valuation comes with the price band. P/E, price-to-book and price-to-sales need an offer price, and draft filings leave it blank. We'll compute them here as soon as the RHP announces the band.
Who is selling
The offer for sale, seller by seller, as the filing itself lists them.
Selling shareholder
Max shares offered
Cost of acquisition
Mohit JanduPromoter
50 lakh
₹2.43
Kuldeep KumarPromoter
50 lakh
₹3.22
Cost of acquisition is the weighted average price the seller originally paid per share, as stated in the filing.
Financials
What J Infratech Limited earned and how, read straight from its DRHP.
One-off items management describes in its own discussion of the results. They are real, but they do not come from day-to-day operations and may not repeat, so an analyst would set them aside when judging the recurring business.
Other
Insurance claims and other reimbursements are recognised when the group has an enforceable right to recovery, the amount can be measured reliably, and no significant uncertainty remains regarding receipt.
Arbitration awards and settlement amounts are recognised when the group's enforceable right to receive the amount is established and the applicable recognition criteria under the relevant Ind AS are satisfied.
Other expenses increased by ₹16.36 Crore, or 75.41%, from ₹21.69 Crore in Fiscal 2025 to ₹38.04 Crore in Fiscal 2026, principally on account of additional one-time expenditure of ₹10.45 Crore incurred for re-development of one of our projects in Himachal Pradesh, which was affected by floods during the year, representing a non-recurring item.
As printed in the filing's summary financial information, converted to ₹ crore.
₹ crore (per-share figures in ₹), as restated in the filing. Click + to see what a line is made of.Source p.86
Line item
FY24
FY25
FY26
Revenue from operations
887
1,411
1,722
Other income
6.3
6.0
9.7
893
1,417
1,731
Income
Finance costs
24
34
52
Depreciation and amortisation expense
23
42
49
772
1,161
1,401
Expenses
Cost of materials consumed
310
408
463
Construction and operating expenses
344
603
756
Purchase of property held as stock in trade
0.00
33
50
Changes in property held as stock in trade
0.00
-33
-50
Employee benefits expense
50
53
43
Other expenses
21
22
38
Restated Profit before tax
123
257
332
37
62
85
Tax expense
Current tax
55
36
58
Income tax adjustment relating to earlier years
-2.0
0.14
0.00
Deferred tax (net)
8.4
0.45
27
86
195
247
Other comprehensive income ('OCI')
Remeasurements gain/(loss) of net defined benefits plan
0.27
0.81
0.26
Income tax relating to above items that will not be reclassified to profit or loss
-0.07
-0.20
-0.07
Restated Other comprehensive income for the year (Net of Tax)
0.20
0.61
0.20
Restated Total comprehensive income for the year
86
196
247
₹ crore (per-share figures in ₹), as restated in the filing. Click + to see what a line is made of.Source p.85
Line item
FY24
FY25
FY26
Property, plant and equipment
133
182
233
Investments in Joint Ventures
1.7
2.4
3.8
279
523
761
Assets
Non-current assets
Investment property
19
26
28
Right of use assets
8.9
8.4
7.2
Intangible assets
0.00
0.24
0.13
Financial assets
Other financial assets
87
272
474
Deferred tax assets (net)
28
28
7.5
Other non current assets
0.22
3.1
6.9
Inventories
8.7
83
212
Trade receivables
35
66
72
Cash and cash equivalents
100
11
78
Bank balances other than cash and cash equivalents
148
106
74
403
483
830
Current assets
Financial assets
Other financial assets
71
117
269
Current tax assets (net)
0.00
19
11
Other current assets
41
80
113
Total assets
682
1,006
1,591
Equity share capital
58
59
117
Other equity
90
286
475
149
345
592
Equity and liabilities
Equity
Borrowings
106
210
350
118
230
375
Liabilities
Non-current liabilities
Financial liabilities
Lease liabilities
8.3
7.9
6.8
Provisions
0.91
0.52
0.90
Deferred tax liabilities (net)
2.8
11
18
Borrowings
145
167
264
- Trade payables total outstanding dues of micro and small enterprises; and
4.7
3.3
7.6
90
89
103
Current liabilities
Financial liabilities
Lease liabilities
0.93
1.1
1.3
415
431
624
Other financial liabilities
31
32
114
Other current liabilities
136
137
134
Provisions
0.00
0.00
0.05
Current tax liabilities (net)
9.9
0.00
0.00
Total liabilities
533
661
999
Total equity and liabilities
682
1,006
1,591
₹ crore (per-share figures in ₹), as restated in the filing. Click + to see what a line is made of.Source p.88
Line item
FY24
FY25
FY26
Restated Profit before tax
123
257
332
Loss/(gain) on disposal of property, plant and equipment (net)
0.06
-0.07
-0.25
Loss/(gain) on disposal of Investment Property (net)
0.00
-0.36
-2.0
Operating profit before working capital changes
166
328
424
162
-129
-55
Adjustments for:
Depreciation and amortisation expense
23
42
49
Finance costs
24
33
52
Remission of Liablity
0.00
0.00
-0.26
Rental Income
-0.02
-0.02
-0.12
Interest income on Fixed deposit
-6.3
-5.4
-5.7
Interest income on Others
-0.03
-0.10
-1.2
Interest on Lease Laibility
0.83
0.79
0.73
Provision of expected credit loss and doubtful loans and advances
1.2
1.4
0.02
Balances Written Off Expenses
1.2
0.03
0.50
Working capital adjustments
(Increase)/decrease in Inventories
-1.5
-74
-129
(Increase)/decrease in Trade receivables
87
-32
-5.3
Increase/(decrease) in Trade payables
39
2.6
16
(Increase)/decrease in Other financial assets
-66
-232
-353
(Increase)/decrease in Other current and non-current assets
-11
-39
-38
Increase/(decrease) in Other financial liabilities
6.5
0.83
82
Increase/(decrease) in Other current liabilities
-27
0.42
-2.0
Increase/(decrease) in Provisions
0.65
0.22
0.61
Cash flows (used in)/from operating activities
195
-47
-5.8
Income taxes paid (net)
-33
-83
-49
-141
-51
-61
Payment for purchase of Property Plant and Equipment(Including Capital work in Progress)4
-97
-92
-98
Payment for purchase of Intangible Assets
0.00
-0.34
-0.00
Proceeds from sale of property, plant and equipment
0.01
0.25
1.4
Rental Income
0.02
0.02
0.12
Payment for purchase of Investment Properties
-1.6
-8.6
-5.1
Proceeds from sale of Investment Properties
0.00
2.0
5.0
Investment made in Joint Ventures
-0.75
-0.67
-1.4
(Investment)/ Redemption in bank deposits
-48
43
32
Interest received
6.5
5.7
5.0
74
91
183
Proceeds from issue of right shares
0.00
0.02
0.00
Proceeds from long term borrowings
170
200
307
Repayment of long term borrowings
-64
-91
-116
Proceeds/ (Repayment) of short-term borrowings (net)
-7.5
18
46
Payment of principal portion of lease liabilities
-0.50
-1.2
-1.2
Payment of interest portion of lease liabilities
-0.83
-0.79
-0.73
Finance cost paid
-24
-33
-52
Net (decrease) in cash and cash equivalents during the year (A+B+C)
95
67
-89
Cash and cash equivalents at the beginning of the year
5.1
100
11
100
11
78
Cash and cash equivalents comprise of:
Balance with banks in current accounts (refer note 12)
69
11
73
Cash on hand (refer note 12)
0.47
0.11
2.2
Fixed deposit
30
0.00
3.0
Discounted cash flow
What J Infratech Limited's cash flow would be worth today. Change the rate, time period or growth to see how sensitive the answer is.
% / yr
years
% / yr
Worth today (10 years of cash)
₹3,882 Cr
Per share
–
Needs the price band.
Top of the price band
–
Projected cash flow (₹ Cr) Worth today at 11% a yearAlong the bottom: years from now
Starts from FY26 net profit of ₹247 Cr, grown 20% a year (based on revenue growth FY24–FY26, capped at 20%) and discounted at 11% a year, with no value counted beyond year 10. A simple illustration from the filing's numbers, not a forecast or investment advice; small changes to the rate or growth move the answer a lot.
The short version
Start here. The story in a few minutes, with every fact tied to the page it came from.
Here's what almost nobody noticed: there's zero verifiable record linking Savitri to the partnership firm during that specific period. That silence, when you're tracking an IPO, tells you something crucial about the company's history.
Corporate Structure and Issuance Process
We need to trace how this company evolved from a partnership to a public entity. It started as the 'Jandu Construction Co.' partnership on April 1, 2005. That partnership was converted into a private limited company on October 19, 2019. Later, the name changed to 'J Infratech Private Limited.'
Read more · 3 points, 6 supporting facts
We need to trace how this company evolved from a partnership to a public entity. It started as the 'Jandu Construction Co.' partnership on April 1, 2005. That partnership was converted into a private limited company on October 19, 2019. Later, the name changed to 'J Infratech Private Limited.'
The company was originally formed as a partnership firm, ‘Jandu Construction Co.’ pursuant to a partnership deed dated April 1, 2005.p.94
The Partnership Firm was converted into a private limited company under the Companies Act, 2013 on October 19, 2019.p.94
The company's name was changed from ‘Jandu Construction India Private Limited’ to ‘J Infratech Private Limited’ pursuant to resolutions passed by the Board and shareholders.p.94
The transition to a public entity involved a final name change. The company converted from a private company to a public limited company, and the name was officially changed from ‘J Infratech Private Limited’ to ‘J Infratech Limited.’
The company was converted from a private company to a public limited company and the name was changed from ‘J Infratech Private Limited’ to ‘J Infratech Limited’.p.94
For the IPO, we see who handled the process. Systematix Corporate Services Limited is listed as the sole Book Running Lead Manager for the offer. And Trilegal is listed as the Legal Counsel to the Company regarding Indian Law.
Systematix Corporate Services Limited is the sole Book Running Lead Manager to the Offer.p.96
Trilegal is listed as the Legal Counsel to the Company as to Indian Law.p.96
Government Contract Dependency and Revenue Risk
A major risk for J INFRATECH is its heavy reliance on contracts awarded by various Government Entities. The company's business is directly exposed to changes in government policies or market conditions, which could lead to contract foreclosures or renegotiations. Specifically, the business is primarily dependent on contracts from entities like NHIDCL, NHAI, MoRTH, BRO, PWD, and Indian Railways.
Read more · 3 points, 6 supporting facts
A major risk for J INFRATECH is its heavy reliance on contracts awarded by various Government Entities. The company's business is directly exposed to changes in government policies or market conditions, which could lead to contract foreclosures or renegotiations. Specifically, the business is primarily dependent on contracts from entities like NHIDCL, NHAI, MoRTH, BRO, PWD, and Indian Railways.
The business is primarily dependent on contracts awarded by various Government Entities.p.27
The business is primarily dependent on contracts awarded by specific Government Entities such as NHIDCL, NHAI, MoRTH, BRO, PWD, and Indian Railways.p.27
This dependency creates a significant concentration risk, as a large portion of the company's revenue comes from just a few key customers. The majority of the revenue from operations is derived from the top two customers, which account for a significant percentage of the total.
Majority of revenue from operations is derived from the top two customers.p.29
Loss of, or reduction in business from, any of these key customers could have a significant adverse impact on cash flows and financial condition.p.29
Furthermore, the revenue generated from executing both EPC and HAM projects makes up a significant portion of the total revenue from operations. We need to keep in mind that there's no assurance that the allocation of EPC projects could change, which could significantly impact future revenues.
The revenue from execution of EPC projects and HAM projects constitutes a significant portion of the Revenue from Operations.p.30
There can be no assurance that there will not be any reduction in the EPC projects allocated to the company, which could significantly impact future revenues.p.30
Litigation and Regulatory Scrutiny
When we look at the company's history, the DRHP flags several past legal issues. For instance, there are no outstanding criminal proceedings against the company itself, as noted on page 471. However, there are past civil claims; specifically, a reference petition was filed by Geosys India Infrastructures Limited concerning non-payment of dues and wrongful retention of machinery, involving amounts up to ₹10.17 Crore and ₹8.40 Crore, which you can find on page 472.
Read more · 3 points, 5 supporting facts
When we look at the company's history, the DRHP flags several past legal issues. For instance, there are no outstanding criminal proceedings against the company itself, as noted on page 471. However, there are past civil claims; specifically, a reference petition was filed by Geosys India Infrastructures Limited concerning non-payment of dues and wrongful retention of machinery, involving amounts up to ₹10.17 Crore and ₹8.40 Crore, which you can find on page 472.
No outstanding criminal proceedings against the company.p.471
A reference petition was filed by Geosys India Infrastructures Limited concerning non-payment of dues and wrongful retention of machinery, involving amounts up to ₹10.17 Crore and ₹8.40 Crore.p.472
The regulatory disclosures also point to past non-compliance issues. The CGST Audit – Commissionerate, Nagpur issued a show cause notice alleging failure to pay and report goods and service tax for a period from April 2020 to March 2023, with dues amounting to ₹12.85 Crore plus interest of ₹3.70 Lakh, as detailed on page 472.
A show cause notice was issued by the CGST Audit – Commissionerate, Nagpur alleging failure to pay and report goods and service tax for a period spanning April 2020 to March 2023, with dues amounting to ₹12.85 Crore and interest of ₹3.70 Lakh.p.472
Furthermore, the filing details several other legal actions. The company has filed a complaint under the Negotiable Instruments Act against Kedareshwar Infrastructure Developers Private Limited and others for dishonored cheques, on page 473. Additionally, a forest offence report was filed against Hari Niwas alleging illegal installation of electric tower poles and illegal possession of land on forest land, also on page 473.
The Company has filed a complaint against Kedareshwar Infrastructure Developers Private Limited and others under the Negotiable Instruments Act, alleging dishonored cheques.p.473
A forest offence report was filed against Hari Niwas alleging illegal installation of electric tower poles and illegal possession of land on forest land.p.473
Who Owns the Company?
Let's look at who the promoters are. The filing shows a significant concentration of ownership before the IPO. Hari Niwas holds the largest stake at 51.00% of the pre-Offer issued equity share capital. This means they control more than half of the company before this new funding round.
Read more · 2 points, 4 supporting facts
Let's look at who the promoters are. The filing shows a significant concentration of ownership before the IPO. Hari Niwas holds the largest stake at 51.00% of the pre-Offer issued equity share capital. This means they control more than half of the company before this new funding round.
Hari Niwas holds 51.00% of the pre-Offer issued, subscribed and paid-up Equity Share capitalp.315
The remaining promoters and related parties hold the rest of the stake. The HN Family Trust accounts for 34.19% of the equity, and Mohit Jandu and Kuldeep Kumar each hold 5.08% individually. This shows a structure where the core promoters have divided their shares among themselves and the trust.
HN Family Trust holds 34.19% of the pre-Offer issued, subscribed and paid-up Equity Share capitalp.315
Mohit Jandu holds 5.08% of the pre-Offer issued, subscribed and paid-up Equity Share capitalp.315
Kuldeep Kumar holds 5.08% of the pre-Offer issued, subscribed and paid-up Equity Share capitalp.315
Bottom line
So, to put it simply, this IPO story boils down to a few key things: heavy reliance on government contracts, past legal claims that have been disclosed, and a specific ownership structure among the promoters. That’s the picture the filing paints—what you make of it is up to you.
Red flags & fact-checks
We looked up selected claims from the filing (promoters, court cases, subsidiaries) on the open web. Here is what we found.
ClearPromoter background
J Infratech Limited
100% confidence
What the filing says
Savitri has no formal education and was associated with the erstwhile partnership firm from April 1, 2010 to October 19, 2019.
No current web search results were found to corroborate, contradict, update, or provide any information regarding the claim about Savitri's formal education or association with the partnership firm during the specified period.
ClearPromoter background
J Infratech Limited
100% confidence
What the filing says
Hari Niwas has been associated with the erstwhile partnership firm from April 1, 2005 to October 19, 2019.
No current web search results were found to corroborate, contradict, update, or provide any information regarding the association of Hari Niwas with the erstwhile partnership firm between April 1, 2005, and October 19, 2019.
ClearPromoter background
J Infratech Limited
100% confidence
What the filing says
Hari Niwas has been a director of the Company from October 19, 2019 to April 11, 2025, and was associated with the erstwhile partnership firm from April 1, 2005 to October 19, 2019.
No current web search results were found to corroborate, contradict, update, or provide any information regarding the claim about Hari Niwas's directorship or association with the erstwhile partnership firm.
ClearPromoter background
J Infratech Limited
100% confidence
What the filing says
Mohit Jandu was appointed as Managing Director on January 27, 2025.
No current web search results were found to corroborate, contradict, update, or provide any information regarding the claim that Mohit Jandu was appointed as Managing Director on January 27, 2025.
ClearPromoter background
J Infratech Limited
100% confidence
What the filing says
Amir Chand was appointed as Chairperson on February 13, 2026.
No current web search results were found to corroborate, contradict, update, or provide any information regarding the claim that Amir Chand was appointed as Chairperson on February 13, 2026.
ClearPromoter background
J Infratech Limited
100% confidence
What the filing says
Mahabir Singh was appointed as an additional non-executive independent director on March 10, 2026.
No current web search results were found to corroborate, contradict, update, or provide any information regarding the appointment of Mahabir Singh as an additional non-executive independent director on March 10, 2026.
Inside the filing
Section-by-section summaries of the Draft Red Herring Prospectus. Turn on Detailed view at the top to expand everything.
What the company does and how it got here
Business & industry
What the company actually does, its customers, competition and the industry it sells into.
The section provides an overview of the economic outlook, detailing projections for global and Indian economic growth, inflation trends, and industrial production. It discusses the resilience of the Indian economy against global challenges, noting strong domestic fundamentals. Furthermore, it outlines trends in disposable income and consumer spending, as well as various Gross Value Added (GVA) sectors, including the construction industry. The text also touches upon the role of government policy, such as capital expenditure allocations, in driving infrastructure-led growth.
The Indian government has allocated significant funds for infrastructure development, focusing heavily on transport and logistics as crucial for economic progress. Key areas include expanding the national highway network, developing access-controlled highways, and improving urban mobility through metro projects. The sector is supported by various government initiatives, Public-Private Partnerships (PPPs), and efforts to integrate logistics through multi-modal parks. While investment is high, the sector is expected to see continued growth driven by these strategic initiatives.
The road transport sector in India plays a significant role in the economy, with road transport contributing 2.3% to India's Gross Value Added in FY25. India handles a substantial volume of goods, with road transport being the dominant mode of freight movement, accounting for approximately 66.6% of freight. The road network is extensive, comprising various types of roads, and its development is crucial for economic growth. Investment in the road sector is projected to see significant growth, driven by infrastructure development plans. Furthermore, the execution of national highway projects has faced slowdowns due to various challenges, while the government is implementing measures to improve project implementation timelines.
This section discusses various financing models for road projects, including Toll-Operate-Transfer (TOT), Infrastructure Investment Trusts (InvITs), and project-based financing. It details the success and performance of these models, noting that the TOT model has attracted significant investor interest. The text also covers the institutional framework for the road sector at the central level, outlining the roles of ministries, autonomous agencies, and state governments. Furthermore, it outlines financial incentives provided by the government to encourage private sector participation in road development and discusses the evolution of Public-Private Partnership (PPP) frameworks.
The text discusses various operational asset monetization models, including Toll-Operate-Transfer (TOT), Infrastructure Investment Trusts (InvITs), and securitisation of toll revenue, which have been used to attract investment and improve efficiency in the sector. It details different Public-Private Partnership (PPP) models such as Build Operate and Transfer (BOT), BOT (Annuity), and Hybrid Annuity Model (HAM), outlining the roles and risk allocation between the government and private developers. Furthermore, the text covers changes in bidding norms by the National Highways Authority of India (NHAI) for Engineering, Procurement and Construction (EPC) projects, and provides an overview of government policies like the Bharatmala Pariyojana and the Central Road Infrastructure Fund (CRIF) scheme.
This section discusses various aspects related to India's infrastructure monetization plans, market dynamics in the road infrastructure sector, and challenges faced by the industry. It details the National Monetisation Pipeline 2.0 (NMP 2.0) and the Viksit Bharat Vision 2047 framework, outlining sectoral contributions to infrastructure monetization targets. Furthermore, it covers market size trends for the road infrastructure industry, including shifts in EPC and HAM segments, and highlights numerous challenges such as land acquisition delays, cash flow mismatches, and various risks related to financing and counterparty relationships.
The text discusses trends in awarding activities related to national highway infrastructure, noting fluctuations in the share of different contract modes over financial years. It also details the importance of road bridges and elevated roads in India's transportation network, mentioning various bridge types and the context of ongoing and upcoming infrastructure projects.
The text discusses the strategic significance of road connectivity in difficult terrain, particularly for defence logistics and economic integration, noting the expansion of national highway networks across various regions. It details the role of agencies like NHIDCL in executing national highways and infrastructure projects in these sensitive areas. Furthermore, the document reviews the attractiveness of different funding models like EPC and HAM for such projects, highlighting risk allocation differences. It also covers the challenges faced by new entrants in these sectors, including geographical, logistical, and regulatory hurdles, and reviews the investment trends in state road infrastructure.
The section details various government initiatives and funding mechanisms related to road infrastructure development across India. It covers funds allocated under the Central Road and Infrastructure Fund (CRIF) for state roads, outlines schemes for Northeastern states like NESIDS, and discusses recent initiatives such as the Pradhan Mantri Gram Sadak Yojana (PMGSY). Furthermore, it projects future investments in state roads, pipeline projects in various states like Maharashtra, Assam, Madhya Pradesh, Uttar Pradesh, Bihar, Arunachal Pradesh, and Himachal Pradesh, focusing on connectivity, urban development, and infrastructure upgrades.
The text details various infrastructure investment plans across different sectors, including road development in Manipur and Telangana, and the ongoing transformation of the Indian Railways. It outlines significant budgetary allocations for road projects, including funding from various sources. Furthermore, it provides an overview of the Indian Railways' modernization efforts, including network electrification targets and plans for capacity expansion through new lines and track renewals. The document also discusses different models for railway projects, such as concessions and joint ventures, and the overall scale of the railway network.
This section details various aspects related to Indian infrastructure and mining sectors, primarily focusing on budgetary allocations for railways and the general landscape of the metals and mining industry. It outlines the significant growth in budget allocation towards railway projects and the government's focus on connectivity in the Northeast Region. Furthermore, it discusses key government initiatives like PM-Gati Shakti and the National Rail Plan, which aim to enhance railway capacity and connectivity. The text also covers growth drivers such as rising passenger travel and the push for freight business, alongside major challenges in the railway sector, including limited financial headroom and operational inefficiencies. Finally, it provides an overview of the mineral production in India, highlighting coal and iron ore as major mined minerals.
The Indian iron ore sector is characterized by significant production, market dynamics, and supply chain considerations. India is the fourth-largest global producer of iron ore, though its reserves require beneficiation for use in steel plants. Production has shown a consistent growth trajectory, supported by capacity expansion and domestic demand. The market involves both captive and non-captive mining, with non-captive production consistently holding a larger share. Iron ore exports have faced headwinds due to weaker demand from China, while imports have surged to meet the need for high-grade ore for specialized steel production. Key growth drivers include rising steel consumption, increased government investment in infrastructure, rapid urbanization, industrialization, and growing purchasing power.
The text describes the various stages in the iron ore value chain, which involves processes from geological exploration to the final use in iron-making facilities. The processing route depends on factors like ore type and required product, ranging from simple crushing for lump ore to complex beneficiation for ultra-fine iron ore. The utilization of iron ore has evolved from directly consuming high-grade lump ore to recovering iron from fines, slimes, and tailings, driven by changes in mining output and technological advancements. This evolution is part of a broader shift towards a circular economy in iron ore mining, encouraging the recovery of accumulated mineral residues.
The company, J Infratech Limited, is an integrated infrastructure engineering, procurement, and construction firm specializing in roads, highways, bridges, and expressways, with a strong track record in large-scale road development projects across India. The company primarily operates in the Business-to-Government (B2G) segment through competitive bidding and has executed projects in challenging terrains across 16 states and 3 Union Territories. The company recently entered the mining and integrated resource management vertical, focusing on the recovery and monetization of iron ore slimes accumulated at the Bacheli Complex in Chhattisgarh. They have secured contracts for the recovery and evacuation of iron ore slimes from both the Bacheli and Kirandul Complexes.
J Infratech Limited is an infrastructure construction company established in 2019, primarily engaged in road and bridge construction across India, operating mainly in the Business-to-Government (B2G) segment through competitive bidding. The company has executed projects in challenging terrains, including the Andaman and Nicobar Islands and states like Assam, Tripura, and Manipur, and maintains a significant order book. The company's key clients include major government bodies such as MoRTH, NHAI, NHIDCL, NMDC, Border Roads Organisation, Railways, and the Government of Telangana, among others. The company commenced operations in 2005 through a partnership firm before converting to the current company in 2019.
The company leverages its contractual obligations under EPC and HAM agreements, along with toll-collection and maintenance projects, to develop its execution capabilities in road infrastructure. The business commenced in 2005 through a partnership firm, which was converted into the current company in 2019. As of July 31, 2026, the company has completed 35 projects and is currently executing 46 projects across 16 states and three union territories. Core strengths include engineering and execution capabilities, supported by a skilled workforce, digital project management systems, AI tools, in-house design, and an owned fleet of machinery.
The company operates within the infrastructure sector, focusing on engineering, procurement, and construction (EPC) projects, particularly in roads and highways, often in challenging terrains. The company leverages its expertise to benefit from increased government allocations for infrastructure projects. They maintain a substantial order book derived from key government agencies like NHAI, NHIDCL, and MoRTH, with long-standing relationships with these entities. The company possesses strong in-house capabilities, including owned equipment and integrated business models, to manage various stages of the project supply chain. Furthermore, the company is expanding into new business verticals such as mining and integrated resource management.
The company is recognized as a fast-growing player in the engineering, procurement, and construction (EPC) infrastructure sector, showing a projected Revenue CAGR of 39.18% according to the CARE Report. The company maintains a diversified order book across various geographical regions, with significant portions dedicated to EPC and HAM projects. The company has established long-standing relationships with key government customers such as NHAI, NHIDCL, MoRTH, and BRO, which validates its execution capabilities. The company relies on a modern, specialized fleet of heavy construction machinery to execute projects and has a strategy to selectively expand into new regions and diversify into complementary sectors like railways and integrated resource management.
The company focuses on infrastructure projects across various geographies, employing automation and advanced tools to optimize workflows and ensure timely, high-quality project delivery. The design process involves detailed planning, design development, design review, and submission for customer approval, often adhering to government circulars. The company utilizes modern materials and engineering solutions, such as Glass Fibre Reinforced Polymer (GFRP) for certain projects, and technologies like Cement Treated Base (CTB) and Cement Treated Sub-base (CTSB) for pavement works. The core business is in the Engineering, Procurement, and Construction (EPC) sector, encompassing activities from survey and design to operation and maintenance. The company has completed 28 EPC projects as of July 31, 2026, and currently has 24 ongoing projects.
The company has executed several projects under various modes, including EPC and HAM (Hybrid Annuity Mode), across different states. Specific projects include rehabilitation and upgradation of a section of the NH-223 in the Andaman & Nicobar Islands, construction of roads in Manipur, and work under the Bharatmala Pariyojna in Madhya Pradesh. Furthermore, the company has numerous ongoing HAM projects in Telangana, involving the construction, upgradation, strengthening, and maintenance of various roads and selected PRED roads under different phases and packages.
This section outlines the detailed procedures for the company's bidding process, which spans from identifying opportunities and analyzing tender documents to developing bid strategies and preparing supporting documentation for submission. Following the bid, the process involves bid evaluation, contract award, and specific requirements for securing performance guarantees for EPC and HAM projects. Project execution involves rigorous planning, mobilization, construction, and continuous monitoring to ensure quality and compliance with contractual specifications. The post-completion phase includes defect liability periods and the eventual handover of projects to the authority.
The company highlights its use of various information technology, digital systems, and management tools to ensure efficient utilization of resources, equipment, and finances, including digital project monitoring and centralized reporting. They employ modern construction equipment and technology-enabled methodologies for infrastructure projects. For engineering and design, they utilize specialized software and digital tools for analysis and optimization, and use cloud-based repositories for document storage. Operational and financial processes are supported by ERP systems and digital workflows, while AI and automation tools are being integrated to enhance employee capabilities in data compilation and reporting. The company emphasizes adherence to strict health, safety, and environmental standards, including compliance with various ISO standards, and obtains necessary permits for projects. The company operates within a competitive environment, facing competition from other EPC companies, and adheres to various Indian laws related to highways.
This section details various Indian laws and regulations pertinent to the road and infrastructure sector, including those governing national highways, tolls, explosives, and environmental compliance. It outlines provisions related to the control of land and traffic on national highways, the power of State Governments to levy tolls, and rules for fee collection on national highways. Furthermore, the text discusses various acts concerning the management and disposal of hazardous and solid waste, as well as regulations concerning industrial operations, worker employment conditions, and environmental impact assessments for projects.
The section details various legal frameworks applicable to the company's operations, primarily concerning labour laws, tax regulations, foreign investment, intellectual property, and general compliance. It outlines numerous acts and codes that govern employment conditions, social security, tax compliance, and the protection of various rights. Furthermore, it lists several other laws that the company must comply with regarding worker rights, such as those related to sexual harassment and disability, alongside various commercial and corporate laws.
Key points (325, showing 60)
Global economic growth is projected to moderate to around 3.1% in 2026, with downside risks potentially reducing it to 2.5% or lower due to geopolitical tensions. p.155
The IMF forecasts GDP growth for India at 6.40% in CY26, which outpaces the estimated global average of 3.00%. p.155
The Union Budget allocated Rs 12.20 lakh crore for capital expenditure in FY27, reinforcing the government's commitment to infrastructure-led growth. p.155
Provisional estimates suggest that India's GDP in FY26 is expected to have grown by 7.75%, supported by strong domestic consumption, investment, manufacturing, and services. p.156
Real GDP growth continued into FY27, with real GDP expanding by 7.8% year-on-year in Q1FY27, above market expectations. p.156
Between January and July 2026, the Consumer Price Index averaged around 3.66%, increasing to 4.45% by July 2026 Year-on-Year. p.157
The Index of Industrial Production (IIP) in India grew by 5.80% Year-on-Year from April-June (FY27), showing steady but moderate industrial momentum. p.158
Gross Value Added (GVA) growth in FY26 (Provisional Estimate) was led by manufacturing, Trade, Hotels, Transport, Communication & Services related to Broadcasting, with industry estimated at 8.5%. p.159
The construction sector contributed 9.0% to the national GVA (at constant price) in FY26. p.159
The residential segment holds the largest share within the construction industry. p.159
The government allocated a record Rs. 11.21 trillion for infrastructure development. p.160
Plans exist to expand the national highway network to 2,0 kilometres by FY37, with 1,46,572 kilometres as of FY26. p.160
The NHAI is expected to award approximately 5,140 kms of road projects in FY27 across EPC, HAM, and other modes. p.160
The government has targeted the operationalisation of 18,000 km of access-controlled National High-Speed Corridors and expressways by FY29 and 26,000 km by FY33. p.160
MoRTH’s identified PPP pipeline of 13,400 km, with an estimated project cost of Rs 8.3 trillion, is expected to support medium-term ordering opportunities. p.160
India has around 1,170 kilometres of operational metro rail across 29 cities as of August 2026. p.160
Approximately 816 kilometres of metro projects are under construction in various cities such as Delhi, Bangalore, Kolkata, Chennai, Kochi, Mumbai, Nagpur, Ahmedabad, Gandhinagar, Pune, Kanpur, Agra, Bhopal, Indore, Patna, Surat, and Meerut. p.160
Opportunities for EPC players are expected to expand with plans to increase operational airports to 220 and add an additional 200 over the next two decades. p.161
The National Highways Authority of India (NHAI), state-level authorities, and domestic and international private sector players drive infrastructure development. p.161
The Smart Cities Mission aims to provide core infrastructure, a clean environment, and better quality of life through smart solutions. p.161
The AMRUT mission focuses on improving basic infrastructure in 500 cities, including water supply, sewerage, stormwater drainage, green spaces, and urban transport. p.161
The PMAY (Pradhan Mantri Awas Yojana) focuses on providing housing for all, with significant emphasis on affordable housing in urban and rural areas through both PMAY-Urban and PMAY-Gramin schemes. p.161
The National Infrastructure Pipeline (NIP) was projected to have an investment of approximately Rs 111 trillion for the period FY 2020–2025. p.163
As of July 2026, 2,545 projects worth Rs 24.2 trillion have been completed, accounting for 29% of the total number of projects in the NIP. p.163
The Bharatmala aims to improve national highway connectivity for better freight and passenger movement. p.164
The Sagarmala focuses on port infrastructure and logistics. p.164
Bharatmala Phase I involves 34,800 km of National Highways. p.164
262 projects worth Rs 1.40 trillion were completed by August 2025 under Bharatmala and Sagarmala. p.164
Road transport contributed 2.3% of India’s total gross value added (GVA) at current prices in FY25, compared with 2.6% in FY24 and 2.5% in FY23. p.165
India handles more than 4.6 billion tonnes of goods each year, with 22% being agricultural goods, 39% mining products, and 39% manufacturing-related commodities. p.165
The road sector budget contributes ~0.9% of total India’s GDP as of FY25. p.165
Road transport accounts for approximately 66.6% of freight movement in India, while rail transport accounts for 23.6% of freight movement. p.166
Road transport accounts for nearly 66.5 percent of the country’s total freight volumes. p.166
India has the second-largest road network in the world, with about 63,45,830 km as of FY26. p.166
National highways account for ~2% of the total road network and ~40% of the total road traffic. p.166
State highways and major district roads account for 60% of traffic and ~98% of road length. p.166
CareEdge research anticipates Rs. 30.31 trillion of investments between FY26 and FY30 in national highways, with an expected CAGR of around 8.3%. p.167
The pace of National Highway construction declined from about 34 km per day in FY24 to around 24-26 km per day in FY26. p.168
Private sector bidding interest in CY19 was largely concentrated in EPC and HAM projects, accounting for about 49.9% and 46.5% of participation, respectively. p.169
By CY25, EPC continued to remain the dominant mode in private sector bidding at about 52.4%, while the share of HAM declined to around 39.7%. p.169
NHAI's outstanding debt increased materially up to FY22 and remained elevated through FY24, stemming from ambitious highway expansion. p.170
NHAI reduced its outstanding debt from Rs 3.35 trillion in FY24 to Rs 2.36 trillion by FY26, supported by toll collections and asset monetization proceeds. p.170
Asset monetization in road projects is undertaken through three routes: toll-operate-transfer (TOT), InvITs, and toll securitisation (SPV). p.170
The Toll-Operate-Transfer (TOT) model attracts bid interest due to its low-risk profile and maturity, allowing private developers to operate roads for a fixed period in exchange for an upfront lump sum. p.170
The success of the TOT model is highlighted by the recent success of TOT Bundle 16, 17, and 18, and NHAI raising ₹15,968.00 Crore in FY24, surpassing targets. p.170
InvITs have mobilized a cumulative ₹43,640.00 Crore till FY25, with the FY25 round being the largest, raising ₹17,740.00 Crore. p.171
NHAI monetized ₹15,950.00 Crore through InvIT Round-5 and the launch of Raajmarg Infra Investment Trust Eoffq in FY26. p.171
Financing through the formation of Special Purpose Vehicles (SPV) can be used to monetize user fee receipts from toll plazas. p.171
Cumulative fund monetized in the road sector from FY19–FY26 amounted to ₹1,67,790.00 Crore. p.171
The market is expected to shift towards InvITs to attract stable, long-term capital, with InvITs scaling up rapidly. p.171
The monetisation target under NMP Phase II has increased to ₹4,14,000.00 Crore, with expected cumulative mobilisation reaching Rs 5,500–5,800 billion during FY27–FY30. p.171
InvITs are estimated to account for about 45–50% of asset monetization during FY26–FY30, followed by 35–37% through TOT and 15–18% through SPV-based models. p.171
The Ministry of Road Transport and Highways (MoRTH) has a Roads Wing for development and maintenance of national highways and a Transport Wing for road transport issues. p.173
The National Highways Authority of India functions as an autonomous agency responsible for the development, operation, and maintenance of the national highways network. p.173
State governments are responsible for the development and maintenance of state highways, major district roads, and rural roads through their Public Works Departments. p.173
The government introduced financial incentives such as bearing the cost of feasibility studies, land, and environmental clearances to attract private sector participation. p.174
The government has introduced provisions like 100% tax exemption for a consecutive 10 years out of 20 years after commissioning a project. p.174
The 'Make in India' initiative encourages the local production of materials and machinery for road construction, boosting self-sufficiency. p.174
The Hybrid Annuity Model (HAM) was introduced to reinvigorate private sector involvement by prioritizing the equitable allocation of risks between stakeholders. p.174
History & corporate structure
How the company came to be: key milestones, subsidiaries, acquisitions and restructurings.
The company originated as a partnership firm, 'Jandu Construction Co.', formed on April 1, 2005, and underwent several structural changes, including conversions to a private limited company and later to a public limited company. The company's name was changed multiple times, culminating in the final name 'J Infratech Limited' following its conversion to a public entity. The company's main objects cover various sectors including government contracting, private works, and the development of infrastructure, including real estate and renewable energy modules. The history also details numerous major project awards and milestones achieved across various states in India.
The section details various compliance and contractual aspects of the company, including assurances regarding borrowings and material transactions over the last ten years. It outlines the absence of certain agreements with strategic partners and clarifies that no guarantees were issued by promoters for the Offer for Sale. Furthermore, it lists several collaboration agreements with members of the promoter group concerning the grant and transfer of development rights for land parcels in Haryana and Gurugram. These agreements involve the Developer having rights over project execution, marketing, and financing.
This section details the shareholding pattern and corporate information for several entities, primarily related to infrastructure projects in Telangana. It lists various private limited companies, including gfiJmoa Peddapally-11 Private Limited, gfiJmoa Nizamabad-10 Private Limited, gfiJmoa Adilabad-1 Private Limited, gfiJmoa Mancherial-7 Private Limited, gfiJmoa Rangareddy-12 Private Limited, and gfiJmoa Warangal-17 Private Limited. It also provides details on their incorporation dates, business objectives (focused on PRED roads under HAM projects), and capital structure, which shows a majority holding by J Infratech Limited and a nominee.
This section details the shareholding patterns and corporate information for several private limited companies. It lists details for JIL-RBD Hanumakonda-5 Private Limited, JIL-RBD Bhadradri-3 Private Limited, JIL-RBD Bhupalapally-8 Private Limited, JIL-RBD Nizamabad-22 Private Limited, JIL-RBD Hanumakonda-4 Private Limited, JIL-RBD Nizamabad-21 Private Limited, gfiJmoa Karimnagar-3 Private Limited, and JIL-RBD Khammam-1 Private Limited. For most entities, the shareholding is dominated by J Infratech Limited, with Kuldeep Kumar as a nominee, and all listed companies have no accumulated profits or losses.
The section details the shareholding pattern of JIL- RBD Khammam-1 Private Limited, which shows J Infratech Limited holding 99.99% of the equity. The company has one Associate, Cerisetech Smart Mobility Testing Private Limited, which was incorporated on March 17, 2026, for the purpose of designing and installing Automated Vehicle Testing Stations in Karnataka. Furthermore, the company has entered into several joint venture agreements for project execution, including agreements with partners like Shiv Buildindia Pvt. Ltd. for a Delhi-Saharanpur-Dehradun economic corridor project, and agreements with Maanbuilders Private Limited for various infrastructure works in Uttar Pradesh and Madhya Pradesh. The text also lists several joint ventures with various partners across different states, such as agreements in Maharashtra, Gujarat, Assam, Manipur, and Karnataka, with various dates spanning from 2018 to 2025.
Key points (59)
The company was originally formed as a partnership firm, ‘Jandu Construction Co.’ pursuant to a partnership deed dated April 1, 2005, in Sirsa, Haryana, India. p.273
The Partnership Firm was registered under the Indian Partnership Act, 1932 bearing firm registration number 1 of 2008 - 2009, issued by the Registrar of Firms, Sirsa, Haryana dated April 7, 2008. p.273
The Partnership Firm was converted into a private limited company under the Companies Act, 2013 under the name of ‘Jandu Construction India Private Limited’ pursuant to a resolution dated July 3, 2019 and a memorandum of association dated October 18, 2019. p.273
The name of the Company was changed from ‘Jandu Construction India Private Limited’ to ‘J Infratech Private Limited’ pursuant to resolutions dated September 4, 2024. p.273
The Company was converted from a private company to a public limited company and the name was changed from ‘J Infratech Private Limited’ to ‘J Infratech Limited’ pursuant to resolutions dated October 15, 2024 and November 4, 2024. p.273
The registered office address was changed from H. No. 323 Aggarsain Colony, SBI Street, Sirsa 125 055, Haryana, India to J-House, B-103, Sector-30, near Signature Tower, Gurugram 122 001, Haryana, India on September 4, 2024, for administrative convenience. p.273
The Memorandum of Association was amended on June 15, 2020 to reflect the addition of a new clause regarding the power to receive money on deposit or loan and borrow or raise money. p.276
The Memorandum of Association was amended on February 11, 2021 to reflect the addition of the preamble of the partnership deed dated April 1, 2018 before Clause I of the Memorandum of Association. p.276
The authorized share capital was increased from ₹10,00,000 divided into 1,00,000 equity shares of ₹10 each to ₹40,00,00,000 divided into 4,00,00,000 equity shares of ₹10 each on March 11, 2021. p.276
The Memorandum of Association was amended on September 18, 2023 to reflect the addition of a new clause regarding the provision of services related to toll collection/user fee collection works. p.276
The name of the Company was changed from ‘J Infratech Private Limited’ to ‘J Infratech Limited’ on September 4, 2024, pursuant to the conversion into a public limited company. p.276
The Memorandum of Association was amended on April 11, 2025 to reflect the addition of new clauses regarding the business of contractors, builders, and developers. p.276
The Memorandum of Association was amended on June 20, 2026 to reflect the addition of new clauses regarding the business of buying, selling, and dealing in mineral products. p.276
The company awarded an EPC project for four-lanning of NH-53 passing through Jalgaon city and construction of vehicular underpass and emergency vehicle underpass in the state of Maharashtra, India in 2019. p.277
The company awarded an EPC project for improvement and widening of two-lane road with paved shoulder of roads in the Jurichhara–Bamanchara section of NH-208 in Tripura, India in 2020. p.277
The company secured a HAM project valued at ₹397.50 Crore for the construction of a new two-lane road with paved shoulders forming part of the Hamirpur Bypass in the state of Himachal Pradesh, India in 2022. p.277
The company awarded an EPC project aggregating to ₹448.50 Crore for construction of a four-lane road in the Barela–Manegaon section in the state of Madhya Pradesh, India in 2022. p.277
The company awarded an EPC project from NHIDCL in Assam aggregating ₹592.80 Crore for four-laning of road in the Dhanehari–Lailapur/Vairengte section of NH-306 in the state of Assam, India in 2023. p.277
The company awarded a HAM project from NHIDCL aggregating ₹696.50 Crore for four-laning and development of a greenfield alignment of the Karimganj–Silchar section of NH-37 in the state of Assam, India in 2024. p.277
The company awarded an NHAI EPC project aggregating ₹598.50 Crore for construction of additional structures, including approaches, in the Vadodara–Surat section of NH-48 in the state of Gujarat in 2024. p.277
The company awarded a project through Border Roads Organisation aggregating ₹24.87 Crore, involving construction of grinder bridges and T-beam bridges in the state of Jammu and Kashmir, India in 2024. p.277
The company awarded an NHIDCL project for rehabilitation of reinforced concrete cement bridge over river Barak at Badarpurghat for ₹2.77 Crore in the state of Assam in 2024. p.277
The company awarded an EPC project through NHIDCL for construction of intermediate lane road and hard shoulder aggregating ₹146.90 Crore in the Hunli-Ithun bridge section on NH-913 in the state of Arunachal Pradesh in 2024. p.277
The company achieved annual revenue in excess of ₹1,000.00 Crore. p.277
The company awarded an EPC project from NHIDCL for balance work for widening/improvement of four lane with paved shoulder configuration of existing lane road from Srirampur (near Bhairiguri Village) to Kachukhana Harichara Paglagaunj (package-I) of Srirampur -Dhubri section of NH-127B in the state of Assam in 2026. p.277
The company awarded an EPC project for construction of the Huri–Taliha section of NH-913 (frontier highway) to intermediate lane in the state of Arunachal Pradesh in 2026. p.277
The company awarded “Outstanding contribution in roads and highways (mid-size project) for the four-lanning with paved shoulders of Kachukhana-Dhubri (NH-127B) section, Assam (JICA, Package II)” by EPC World Media Group in 2026. p.277
The company awarded “Excellence in Infrastructure Development & Execution” by EPC World Media Group in 2026. p.277
The company awarded “Engineering excellence next-gen highway technology” by Roadx Excellence Awards in 2026. p.277
The company does not have any significant financial or strategic partnerships as on the date of this Draft Red Herring Prospectus. p.277
There has been no instance of default, rescheduling or restructuring of borrowings with financial institutions or banks in respect of borrowings from lenders. p.278
Our Company has not entered into any subsisting material agreements with strategic partners, joint venture partners and/or financial partners other than in the ordinary course of business of our Company. p.278
Our Company has not made any material acquisitions or divestments of business/undertakings, mergers, amalgamation, any revaluation of assets etc. in the last 10 years. p.278
A Collaboration Agreement 1 was entered into between J Estates Private Limited and the Company for the grant and transfer of development rights of land parcels in Hisar, Haryana. p.279
A Consultancy Agreement was entered into between Hari Niwas (Promoter) and the Company for availing consultancy and advisory services in infrastructure development, project management, finance and operations. p.280
As on the date of this Draft Red Herring Prospectus, the Company has seventeen wholly-owned Subsidiaries, thirteen Joint Ventures, and one Associate. p.281
Hamirpur Byepass Private Limited was incorporated on November 7, 2022, for the construction of a new two-lane road for the Hamirpur Bypass in Himachal Pradesh. p.281
Jandu Silchar Highway Private Limited was incorporated on April 23, 2024, to execute a project for four-laning and greenfield alignment of a section of NH-37 in Assam. p.282
gfiJmoa Khammam-4 Private Limited was incorporated on June 26, 2026, to execute a project for the construction and maintenance of Panchayat Raj Engineering Department roads in Telangana. p.282
J Infratech Limited holds 99.99% of the shareholding in gfiJmoa Peddapally-11 Private Limited. p.283
gfiJmoa Rangareddy-12 Private Limited was incorporated on July 7, 2026. p.286
JIL-RBD Hanumakonda-4 Private Limited was incorporated on July 09, 2026. p.291
JIL-RBD Hanumakonda-4 Private Limited was incorporated to execute the Project for the widening, strengthening & maintenance of selected R&BD roads in the Hanumakonda 1 package in Telangana under HAM, Phase -I -Package No. 4. p.291
gfiJmoa Karimnagar-3 Private Limited was incorporated to execute the Project- Construction, upgradation, strengthening and maintenance of selected PRED roads in the Karimnagar circle in Telangana under a HAM, Phase-I, Package No. 3. p.292
J Infratech Limited holds 99.99% of the equity in JIL- RBD Khammam-1 Private Limited as of the Draft Red Herring Prospectus date. p.293
Cerisetech Smart Mobility Testing Private Limited was incorporated on March 17, 2026, pursuant to a certificate of incorporation issued by the Registrar of Companies, Central Registration Centre. p.293
Cerisetech Smart Mobility Testing Private Limited was incorporated to design, develop, establish, construct, install, commission, operate, manage and maintain Automated Vehicle Testing Stations (AVTS) in the State of Karnataka. p.293
A joint venture agreement was entered into with Shiv Buildindia Pvt. Ltd. for the development of a six lane access control greenfield highway of Delhi-Saharanpur-Dehradun economic corridor. p.294
A joint venture agreement was entered into with Maanbuilders Private Limited for the construction of a 4-lane from Barela to Manegaon section of NH-30. p.294
A joint venture agreement was entered into with Maanbuilders Private Limited for a contract for improvement and widening of a road section in Tripura. p.294
A joint venture agreement was entered into with Shri Swami Samarth Engineers Limited for the construction of 11 standalone safety structures/works on various NHs in the State of Maharashtra. p.294
A joint venture agreement was entered into with L B Kunjir for the improvement and widening of a road section in Maharashtra. p.294
A joint venture agreement was entered into with AzVirt Limited for the construction of additional structures including approaches in the Vadodara–Surat section of NH-48. p.294
A joint venture agreement was entered into with Assam R & C Infraengineers Pvt. Ltd for the balance work for widening/improvement to a single lane road in Assam. p.295
A joint venture agreement was entered into with Niraj Cement Structurals Ltd for the construction of a two lane with paved shoulders road in Manipur. p.295
A joint venture agreement was entered into with Ram Kumar Contractor for the construction of flyovers in Aloka City in the state of Maharashtra. p.295
A joint venture agreement was entered into with Rajendra Singh Bhamboo Infra Private Limited for the rehabilitation and upgradation of an existing carriageway in Maharashtra. p.295
A joint venture agreement was entered into with Prasad Thekedar and Navbharat Buildcon Private Limited for a sub-project in District – Hanumangarh. p.296
A joint venture agreement was entered into with JSP Projects Private Limited for the contract for rehabilitation and augmentation of a road section in Arunachal Pradesh. p.296
The IPO terms and where the money goes
Cover & definitions
Headline offer terms and the glossary the rest of the document relies on.
This section provides definitions for various terms used in the Draft Red Herring Prospectus. It specifies that 'Our Company' is J Infratech Limited, a public limited company incorporated under the Companies Act, 2013, with a registered office in Gurugram and a corporate office in Hisar. The definitions also detail various roles such as the Chairperson (Amir Chand), Chief Financial Officer (Vishal Puri), Company Secretary and Compliance Officer (Gunjan Arora), and the Managing Director (Mohit Jandu). Furthermore, it defines key entities like Promoters (Mohit Jandu, Hari Niwas, Kuldeep Kumar, Savitri and HN Family Trust) and the Statutory Auditors (S S Kothari & Co. LLP).
This section details various agreements, participants, and timelines related to the offer process, including agreements with various banks, participants, and the process for fund transfer. It defines terms such as Cash Escrow, Depository Participants, Cut-Off Price, and various categories of bidders like Retail Individual Investors (RIIs) and Qualified Institutional Buyers (QIBs). It also specifies designated branches, locations, and the date for fund transfer to the public offer account.
This section primarily defines various terms used within the Draft Red Herring Prospectus, covering aspects related to investor participation, regulatory frameworks, and financial metrics. It details requirements for investors using the UPI mechanism, the various circulars governing such mechanisms, and definitions for financial, legal, and industry-specific terms. Several definitions relate to various laws, financial instruments, and corporate structures.
This section primarily defines various Key Performance Indicators (KPIs) and financial measures used in the Draft Red Herring Prospectus. It details calculations for metrics such as Revenue from Operations, EBITDA, Profit After Tax (PAT), Net Worth, Debt-Equity Ratio, and various days metrics like Inventory Days and Trade Receivable Days. The text also outlines conventions regarding the use of financial information, the source of industry and market data, and the currency used for presentation.
This section primarily discusses forward-looking statements and the various risks that could cause actual results to differ from expectations. Key risks highlighted include dependency on contracts with Government Entities, reliance on top two customers, concentration of revenue from EPC and HAM projects, issues with competitive bidding for projects, geographical concentration of the order book, implementation risks in construction, and working capital requirements. The company is also pursuing new business ventures and diversification efforts.
Key points (30)
The company is J Infratech Limited, a public limited company incorporated under the Companies Act, 2013. p.4
The registered office of the company is situated at J House, Plot 93, Sector 44, Gurugram, Sector 45, Gurgaon 122 003, Haryana, India. p.4
The corporate office of the company is situated at Kothi No 39 Model Town, Mandi Adampur, Hisar 125 052, Haryana, India. p.4
The Managing Director of the Board is Mohit Jandu. p.5
The Promoters of the company include Mohit Jandu, Hari Niwas, Kuldeep Kumar, Savitri and HN Family Trust. p.5
The Statutory Auditors are S S Kothari & Co. LLP. p.6
An agreement is to be entered into between the Company, Promoter Selling Shareholders, the Registrar to the Offer, the BRLM, Syndicate Member, the Escrow Collection Bank, the Public Offer Account Bank, the Sponsor Banks, and the Refund Bank for the collection of bid amounts and transfer of funds. p.9
Only Retail Individual Investors in the Retail Category and Eligible Employees Bidding in the Employee Reservation Portion are entitled to Bid at the Cut-off Price. p.9
The Designated Date is the date on which funds from the Escrow Account are transferred to the Public Offer Account or the Refund Account, as appropriate. p.9
QIBs who Bid in the Offer are subject to a portion of the Offer being not more than 50% of the Net Offer. p.11
The Offer for Sale is defined as the offer for sale of up to 1,00,00,000 Equity Shares of face value of ₹10 each aggregating to ₹[●] million by the Promoter Selling Shareholders. p.11
The Public Offer Account Bank is defined as a clearing member and registered with SEBI as a banker to an issue, with whom the Public Offer Account will be opened for collection of bid amounts. p.11
The Price Band ranges from a Floor Price to a Cap Price, where the Cap Price is at least 105% of the Floor Price and not greater than 120% of the Floor Price. p.12
The Pre-IPO Placement, if undertaken, shall not exceed 20% of the size of the Fresh Issue. p.12
The Offer Price will be decided by the Company in consultation with the BRLM on the Pricing Date, in accordance with the Book-Building Process. p.12
The Retail Category Portion is not less than 35% of the Net Offer and is available for allocation to Retail Individual Investors. p.13
Individual investors applying in public issues with an amount up to ₹5,00,000 are required to use the UPI Mechanism and provide their UPI ID. p.14
UPI Bidders must submit their application with a syndicate member, a stock broker, a depository participant, and a registrar and share transfer agent. p.14
UPI Circulars include SEBI circular number SEBI/HO/CFD/DIL2/CIR/P/2019/85 dated July 26, 2019, and various Stock Exchange circulars. p.14
The definition of 'Working Day' is specified for both the bid/offer period and the time between the closing date and listing. p.14
The definition of 'EPC Order Book (%)' is calculated as the unexecuted value of EPC contracts divided by the total Order Book. p.18
Financial information is derived from the Restated Consolidated Financial Information for Fiscals 2026, 2025, and 2024. p.20
Non-GAAP financial measures are not a measurement of financial performance or liquidity under Ind AS, Indian GAAP, IFRS, or U.S. GAAP and should not be considered in isolation. p.21
The currency used for presentation includes Indian Rupees (INR) and United States Dollars (USD), with exchange rates provided for March 31, 2026, 2025, and 2024. p.23
A significant portion of the company's Revenue from Operations is derived from contracts with Government Entities. p.24
Majority of the company's Revenue from Operations is derived from its top two customers. p.24
Revenue from execution of EPC projects and HAM projects constituted a high percentage of Revenue from Operations. p.24
The Order Book is geographically concentrated in specific Indian states. p.24
The company is exposed to risks arising from economic, regulatory, and other changes in the states where its revenue is concentrated. p.25
The company has recently entered into a new business venture and seeks to diversify into new business verticals. p.25
The offer
How many shares are being sold, by whom, and on what terms.
This section details the corporate history of the company, tracing its evolution from a partnership firm to a private limited company and subsequently to a public limited company. It outlines various name and incorporation changes that occurred over several years, including the conversion of the company structure. The text also provides information regarding the various parties involved in the offering process, such as the Book Running Lead Manager, Registrar, and legal counsel.
This section details various procedural aspects related to the issuance, including the availability of lists for RTAs and CDPs, the lack of an appointed credit agency for grading, and the plan to appoint a monitoring agency for the utilization of proceeds. It also outlines the book-building process, which involves determining the price band and minimum bid lot in consultation with the Bid/Running Lead Manager (BRLM). Furthermore, it specifies mandatory participation methods for different investor categories and the process for entering into an underwriting agreement with underwriters.
Key points (14)
The company was originally formed as a partnership firm, ‘Jandu Construction Co.’, pursuant to a partnership deed dated April 1, 2005. p.94
The Partnership Firm was converted into a private limited company under the Companies Act, 2013 on October 19, 2019. p.94
The company's name was changed from ‘Jandu Construction India Private Limited’ to ‘J Infratech Private Limited’ pursuant to resolutions passed by the Board and shareholders. p.94
The company was converted from a private company to a public limited company, and the name was changed from ‘J Infratech Private Limited’ to ‘J Infratech Limited’. p.94
Systematix Corporate Services Limited is the sole Book Running Lead Manager to the Offer. p.96
Trilegal is listed as the Legal Counsel to the Company as to Indian Law. p.96
KFin Technologies Limited is listed as the Registrar to the Offer. p.96
No credit agency registered with SEBI has been appointed for grading for the Offer. p.99
The Company will appoint a monitoring agency prior to the filing of the Red Herring Prospectus in accordance with Regulation 41 of SEBI ICDR Regulations for monitoring the utilization of proceeds from the Fresh Issue. p.99
The Book building process involves determining the Price Band and Employee Discount in consultation with the BRLM and the minimum Bid lot in consultation with the BRLM. p.100
All investors (other than Anchor Investors) must participate in the Offer mandatorily through the ASBA process or the UPI Mechanism. p.100
Investors are advised to make their own judgment about investment through the Book Building process prior to submitting a Bid. p.100
The Company and Promoter Selling Shareholders will enter into an Underwriting Agreement with the Underwriters after the determination of the Offer Price but prior to filing the Prospectus with the RoC. p.100
The Underwriters are registered with the SEBI under Section 12(1) of the SEBI Act or registered as brokers with the Stock Exchange(s). p.100
Capital structure
Who owns what today, past share issues and what the shareholding looks like after the IPO.
This section details the authorized and issued share capital of the company as of the Draft Red Herring Prospectus date, including various components of the offer structure. It outlines the authorized share capital, the issued and paid-up share capital before the offer, and various provisions related to the offer, such as fresh issues, offers for sale, and employee reservation portions. Furthermore, the text provides historical details on the allotment of equity shares, including various rights issues and bonus issues, as well as information on secondary transactions and the history of the company's share capital.
The company has not issued any equity shares out of revaluation reserves or pursuant to schemes of arrangement approved under Sections 230-234 of the Companies Act, 2013. The company has also not made any issuance of equity shares under employee stock option schemes as of the date of this Draft Red Herring Prospectus. The history of promoter shareholding shows that promoters collectively hold 97.66% of the issued equity share capital. Various transactions, including allotments, rights issues, and bonus issues, have occurred over time, involving transfers and gifts between various parties.
The section details various aspects of the company's capital structure, including the treatment of initial allottees' account balances and the status of promoter shareholding. It confirms that no preference shares have been allotted by the promoters since the company's incorporation and that all equity shares held by the promoters were fully paid-up upon allotment. Furthermore, it asserts that no equity shares held by the promoters are currently subject to pledge with any creditor or other encumbrance. The text also provides extensive details on the shareholding pattern of various shareholders, including promoter group members, and information regarding the minimum promoter's contribution requirements and lock-in periods for equity shares.
This section presents the shareholding pattern of the company as of September 25, 2024, detailing the pre-Offer and post-Offer shareholding percentages across different price bands. It provides a breakdown of equity shareholding for various promoters and the Promoter Group, including individual shareholders and the HN Family Trust. Furthermore, the section lists details of various transactions involving the acquisition of equity shares by promoters and promoter selling shareholders, such as transfers, gifts, and bonus issues.
Key points (39)
The authorized share capital is set at 15,00,00,000 Equity Shares with a face value of ₹10 each, aggregating to ₹1,50,00,00,000. p.102
The issued, subscribed, and paid-up share capital before the offer is 11,69,91,060 Equity Shares with a face value of ₹10 each, aggregating to ₹1,16,99,10,600. p.102
The Board authorized the Offer pursuant to a resolution dated September 21, 2026, and shareholders authorized the Fresh Issue pursuant to a special resolution dated September 22, 2026. p.102
Promoter Selling Shareholders, including Mohit Jandu and Kuldeep Kumar, consented to the inclusion of their respective portions of the Offered Shares for Sale. p.102
Mohit Jandu consented to sell up to 50,00,000 Equity Shares for an amount aggregating up to a certain value. p.102
Kuldeep Kumar consented to sell up to 50,00,000 Equity Shares for an amount aggregating up to a certain value. p.102
The Employee Reservation Portion shall not exceed 5% of the post-Offer Equity Share capital. p.102
The history of equity share allotments includes an initial subscription on October 19, 2019, involving various allottees. p.103
A rights issue occurred on March 31, 2021, involving a ratio of 319 Equity Shares for every one fully paid-up Equity Share held. p.103
A rights issue occurred on September 30, 2024, involving a ratio of one Equity Shares for every 2,924 fully paid-up Equity Shares held. p.104
A bonus issue occurred on February 16, 2026, involving a ratio of one Equity Share for every one Equity Share held. p.104
A bonus issue occurred on May 25, 2022, involving a ratio of 100 Equity Shares for every 631 Equity Shares held. p.105
Promoters hold an aggregate of 11,42,58,262 Equity Shares, constituting 97.66% of the issued, subscribed and paid-up equity share capital. p.107
A bonus issue was conducted on February 13, 2026, in the ratio of one Equity Share for every one Equity Share held. p.108p.111
A transfer of 2,57,00,000 Equity Shares occurred on March 17, 2026, to Hari Niwas by way of gift. p.108p.111
A transfer of 30,26,871 Equity Shares occurred on June 24, 2026, by Kuldeep Kumar by way of gift. p.108p.111
A transfer of 94,06,081 Equity Shares occurred on September 21, 2026, by Mohit Jandu by way of gift. p.108p.111
A transfer of 4,00,00,000 Equity Shares occurred on March 18, 2026, to HN Family Trust by way of gift. p.109p.111
A transfer of 1,19,56,486 Equity Shares occurred on September 23, 2026, to Hari Niwas by way of gift. p.109p.111
Initial Allottees' current account balances were transferred to the company as unsecured loans and adjusted against share application money. p.112
No preference shares have been allotted by the Promoters since the incorporation of the Company. p.112
All Equity Shares held by the Promoters were fully paid-up on the respective date of allotment/acquisition. p.112
None of the Equity Shares held by the Promoters are subject to pledge with any creditor or any other encumbrance as of the Draft Red Herring Prospectus date. p.112
The aggregate of Promoters' shareholding in excess of 20% shall be considered as minimum promoters’ contribution and locked-in for 18 months. p.113
The entire pre-Offer Equity Share capital will be locked in for a period of six months from the date of Allotment, except for certain exceptions. p.113
Certain Equity Shares offered for Promoters’ Contribution do not include shares acquired during the three years preceding the date of the Draft Red Herring Prospectus for consideration other than cash and revaluation of assets or capitalization of intangible assets. p.113
The Promoter’s Contribution does not include any Equity Shares acquired during the one year preceding the date of the Draft Red Herring Prospectus at a price lower than the offer price. p.113
No Equity Shares have been issued in the one year immediately preceding the date of the Draft Red Herring Prospectus pursuant to the conversion of a partnership firm. p.113
The entire pre-Offer Equity Share capital will be locked in for six months pursuant to Regulation 17 of the SEBI ICDR Regulations. p.113
50% of Equity Shares Allotted to Anchor Investors shall be locked in for 90 days and the remaining 50% for 30 days. p.114
No Promoters, members of the Promoter Group, Directors, or their relatives have sold or purchased any Equity Shares during the six months preceding the Draft Red Herring Prospectus date. p.114
The total equity shareholding as on September 25, 2024, was 100.00% p.117
Hari Niwas held 51.00% of the pre-Offer equity share capital. p.117
Mohit Jandu held 5.08% of the pre-Offer equity share capital. p.117
The total shareholding of Promoters and members of the Promoter Group was 100.00% of the pre-Offer paid-up Equity Share capital. p.117
Kuldeep Kumar transferred 30,26,871 equity shares to Hari Niwas by way of a gift on June 10, 2024. p.118
A transfer from Kuldeep Kumar by way of a gift occurred on September 10, 2026, involving 1,17,60,000 equity shares. p.118
A transfer from Savitri by way of a gift occurred on September 10, 2026, involving 1,19,56,486 equity shares. p.118
A transfer from Priya by way of a gift occurred on June 10, 2022, involving 13,36,399 equity shares. p.118
Use of proceeds
What the money raised will be spent on: growth, debt repayment or promoters cashing out.
The Offer comprises both a Fresh Issue and an Offer for Sale, with the proceeds from the Offer for Sale not forming part of the Net Proceeds. The proposed utilization of the Net Proceeds is intended for funding working capital requirements, pre-payment or re-payment of outstanding borrowings, and general corporate purposes. The company also anticipates benefits from the listing of equity shares and enhanced brand name recognition. The utilization of funds is subject to various estimates, and the deployment schedule is projected across fiscal years.
This section details various financial metrics, primarily concerning the aging of current assets and liabilities, and outlines the intended use of net proceeds from the offer. The text provides assumptions and justifications for the holding levels of inventory, trade receivables, unbilled revenue, other current assets, trade payables, other financial liabilities, and other current liabilities over several fiscal years. Furthermore, it discusses the process for pre-payment or repayment of outstanding borrowings and the general corporate purposes for utilizing the net proceeds.
The section discusses various regulatory requirements concerning the utilization of Gross Proceeds, including provisions for disclosure and certification by the statutory auditor. It outlines the company's obligations to disclose the uses and applications of these proceeds on a quarterly basis to the Audit Committee and annually until all proceeds are utilized. Furthermore, it details the requirements for furnishing statements to Stock Exchanges regarding deviations in the utilization of funds. The text also covers stipulations on the interim use of Net Proceeds, including depositing them in scheduled commercial banks, and confirms that the company will not use these proceeds for trading in other listed company shares.
The provided section details various Key Performance Indicators (KPIs) for the company, categorized into operational and financial metrics. It outlines the methodology for calculating these KPIs and clarifies that these metrics are supplemental and should not be considered in isolation from the Restated Consolidated Financial Information. The text also includes a comparison of these KPIs against listed industry peers across different fiscal years.
This section details various financial and operational metrics for the company across fiscal years 2026, 2025, and 2024, including Return on Capital, Inventory Days, Trade Receivable Days, Creditor Days, and Net Operating Cycle. It also covers provisions related to the issuance and sale of equity shares, including restrictions on primary and secondary transactions. The section concludes with explanations regarding the determination of the Offer Price and Cap Price based on various factors and the importance of reading other sections of the prospectus for a complete understanding.
This section details the statement of possible special tax benefits available to J Infratech Limited, its subsidiaries, and shareholders under various Indian tax laws for the purpose of an Initial Public Offering (IPO). The document outlines the responsibilities of the Company's management and the statutory auditors regarding the preparation and maintenance of these records. It confirms that the statement is intended to provide general information to investors, and clarifies that certain benefits are special tax benefits, distinguishing them from general tax benefits.
This section details the possible special tax benefits available to the Company, its Material Subsidiaries, and its shareholders under various Indian Tax Regulations. It discusses concessional corporate tax regimes under sections 200 for the Company and Material Subsidiaries, noting that these options are preserved under the Income-tax Act, 2025. Furthermore, it outlines various tax benefits for shareholders, including deductions on inter-corporate dividends and concessional tax rates on short-term and long-term capital gains, subject to specific conditions.
Key points (35)
The Fresh Issue and the Offer for Sale aggregate up to a certain amount. p.122
Proceeds received from the Offer for Sale will not form part of the Net Proceeds. p.122
The proposed utilization of funds includes funding working capital requirements. p.123
The proposed utilization of funds includes pre-payment or re-payment of outstanding borrowings. p.123
The proposed utilization of funds includes general corporate purposes. p.123
The amount to be utilized for general corporate purposes shall not exceed 25% of the Gross Proceeds. p.123
Inventory days increased from 10 days in Fiscal 2024 to 41 days in Fiscal 2025 and further to 87 days in Fiscal 2026. p.127
Trade receivable days were 15 days in Fiscal 2024, 19 days in Fiscal 2025, and 16 days in Fiscal 2026. p.127
Other current assets remained broadly stable at 22 days, 24 days, and 21 days in Fiscal 2024, Fiscal 2025, and Fiscal 2026, respectively. p.128
Trade payable days declined from 58 days in Fiscal 2024 to 40 days in Fiscal 2025 and further to 37 days in Fiscal 2026. p.128
Other financial liabilities days stood at 13 days in Fiscal 2024, declined to nine days in Fiscal 2025, and increased to 25 days in Fiscal 2026. p.128
Other current liabilities days decreased from 62 days in Fiscal 2024 to 39 days in Fiscal 2025 and further to 30 days in Fiscal 2026. p.128
General corporate purposes include meeting ongoing general corporate exigencies, strengthening marketing capabilities, acquisition of fixed assets, and payment of taxes and duties. p.130
The company must disclose the purposes for which Net Proceeds have been utilized in its balance sheet. p.132
The company shall disclose the uses and applications of Gross Proceeds to the Audit Committee on a quarterly basis pursuant to Regulation 18(3) and Regulation 32(3) of the SEBI Listing Regulations. p.132
The company shall prepare an annual statement of funds utilized for purposes other than those stated in the DRHP and place it before the Audit Committee until all Gross Proceeds are utilized. p.132
The company shall furnish quarterly statements to Stock Exchanges indicating deviations in the actual utilization of the proceeds from the objects stated in the DRHP. p.132
The Net Proceeds shall be retained in the Public Offer Account until receipt of listing and trading approvals from the Stock Exchanges. p.132
The company confirms it shall not use the Net Proceeds for buying, trading, or otherwise dealing in shares of any other listed company or for any investment in the equity markets. p.132
The company shall not vary the objects of the Fresh Issue without authorization from the Shareholders by way of a special resolution. p.132
The management and Audit Committee have confirmed that disclosed KPIs comply with SEBI ICDR Regulations and a specific circular. p.137
Verified details of the KPIs have been included in the section and subjected to certification by MRKS and Associates. p.137
The company confirms it will continue to disclose KPIs periodically for one year after listing or until fresh issue utilization. p.137
Order Book is used to indicate the visibility of future revenue for the company. p.139
The company has not made any material acquisitions or dispositions to its business during the fiscal years 2026, 2025, and 2024. p.142
The company has not issued any equity shares or convertible securities, excluding the issuance of bonus shares, during the 18 months preceding the date of the Draft Red Herring Prospectus, where such issuance was equal to or more than 5% of the paid-up share capital in a single transaction or multiple transactions combined over a span of rolling 30 days (Primary Issuance). p.144
There have been no secondary sales/acquisitions of Equity Shares or any convertible securities by parties related to the Promoter Group during the 18 months preceding the date of the Draft Red Herring Prospectus, where the transaction was equal to or more than 5% of the paid-up share capital in a single transaction or multiple transactions combined over a span of rolling 30 days (Secondary Transactions). p.144
A rights issue was conducted on September 30, 2024, in the ratio of one equity share for every 2,924 fully paid-up equity shares held. p.144
A bonus issue was conducted on February 16, 2026, in the ratio of one equity share for every one equity share held. p.144
Details of five secondary transactions involving transfers by gift were provided, including transactions involving Hari Niwas, Mohit Jandu, Monika, and Priya. p.145
The Company is eligible to be taxed under section 200 of the Income-tax Act, 2025 for Tax Year 2026-27 and subsequent tax years. p.152
The income-tax payable by an eligible domestic company under the section 200 regime is 22% of total income, with a resulting effective tax rate of 25.168% for Tax Year 2026-27. p.152
The Material Subsidiaries are eligible to be taxed under section 200 of the Income-tax Act, 2025, subject to computation restrictions and other conditions. p.153
A domestic corporate shareholder may be eligible for a deduction in respect to dividend income received from the Company, subject to prescribed conditions under section 148. p.154
Short-term capital gains arising from the transfer of Equity Shares of the Company may be chargeable to income-tax at the rate of 20% plus applicable surcharge and Health and Education Cess. p.154
The numbers behind the story
Financial information
Revenue, profit, debt, cash flow and the auditors' notes behind them.
This section details the scope of the independent auditor's examination over the restated consolidated financial information of J Infratech Limited for inclusion in the Draft Red Herring Prospectus (DRHP). It outlines the financial information covered for various financial years, including the restated consolidated statement of assets and liabilities, profit and loss, cash flows, and changes in equity. The information pertains to financial years ending March 31, 2026, March 31, 2025, and March 31, 2024. The section also clarifies the relationship between different financial statements, including the inclusion of financial information from subsidiaries and the transition to Indian Accounting Standards (Ind AS).
The financial information presented was prepared in accordance with Ind AS 101, incorporating mandatory exceptions and optional exemptions selected by the Company. The financial statements for the years ended March 31, 2025, and March 31, 2024, were derived from Audited Indian GAAP Financial Statements and the financial statements of Historical Subsidiaries and joint ventures. The Prior Period Restated Consolidated Financial Information was examined by the Previous Auditor, and the examination relied upon the Prior Period Restated Consolidated Financial Information and the auditor's report. The examination also relied on various audit and examination reports from Component Auditors for the financial years ended March 31, 2026, 2025, and 2024.
This section primarily details the audit and examination reports related to various subsidiaries, joint ventures, and the company's financial statements for different fiscal years. It lists numerous reports covering financial years ending March 31, 2024, 2025, and 2026, involving different auditors like S S Kothari Mehta & Co. LLP and Mohit Bharti & Associates. The reports cover consolidated and standalone financial statements, as well as special purpose financial statements, for entities such as J Infratech Limited, Jandu Silchar Highway Private Limited, Hamirpur Byepass Private Limited, and various Joint Ventures.
This section primarily contains audit and examination reports for various joint ventures and entities covering financial years ended March 31, 2026, 2025, and 2024. The reports were conducted by Mohit Bharti & Associates and include audit opinions for several entities such as JIL Azvirt JV, R&C IEPL JIL JV, Ram Kumar Jandu JV, and RSBIPL Jandu JV, for both the 2026 and 2025 periods. There are also examination reports covering multiple years for certain entities.
This section presents the restated consolidated financial information for J Infratech Limited, including the Profit and Loss statement, Cash Flow statement, and changes in equity, for the years ended March 31, 2026, 2025, and 2024. The financial information has been prepared in accordance with various Indian Accounting Standards and regulations. The company is primarily engaged in civil construction and infrastructure development projects. The information is derived from audited financial statements and includes adjustments for changes in accounting policies and other required restatements.
This section details the accounting policies and presentation requirements for restated consolidated financial information, including the basis of consolidation for subsidiaries and joint ventures. It outlines various aspects of revenue recognition, covering EPC contracts, service concession arrangements (like HAM road projects), operation and maintenance (O&M) services, toll management, and the transfer of land or development rights. The text also specifies how to account for contract balances, variable consideration, and the treatment of various contractual adjustments.
This section details various accounting treatments and recognition criteria for different financial items, including income, property, intangible assets, investment property, financial instruments, inventories, and provisions. It outlines specific rules for recognizing items like interest income, insurance claims, and contingent liabilities based on established accounting standards (Ind AS). Furthermore, it specifies how various assets and liabilities are measured, depreciated, impaired, and how financial instruments are classified and subsequently measured. The text also covers rules for handling tax recognition, employee benefits, and borrowing costs.
This section details various accounting treatments related to leases, commitments, cash flow statement preparation, consolidation policies, and asset accounting. It outlines how different types of contracts are classified as leases, the initial measurement and subsequent changes to Right-of-Use (ROU) assets and lease liabilities, and the classification of lease payments into operating or financing cash flows. Furthermore, it discusses the treatment of commitments, intra-group funding, joint ventures, and the accounting for costs related to construction and contract execution.
This section details the financial information for J Infratech Limited, covering Investment Property, Leases and Right-of-Use Assets, Other Intangible Assets, Investments in Joint Ventures, Other Financial Assets, Tax assets/liabilities, Other assets, and Inventories. The data is presented across various reporting dates, showing movements in carrying values, additions, disposals, and depreciation/amortization. Specific notes clarify accounting policies, such as the election to continue using carrying values under previous GAAP and disclosures regarding pledged assets and related party transactions.
This section provides detailed financial information covering trade receivables, cash balances, equity structure, and borrowings. It details the ageing of trade receivables across different timeframes, outlines various bank balances, and lists the composition and details of the company's borrowings, including secured and unsecured loans. Furthermore, it includes disclosures regarding the company's equity share capital, retained earnings, and other comprehensive income.
This section details various aspects of the financial structure and liabilities of J Infratech Limited, including security arrangements with lenders and the breakdown of borrowings and provisions. It outlines charges on company assets, various guarantees provided by directors, and details concerning borrowings, lease liabilities, and provisions for employee benefits. Furthermore, it presents the components of revenue, cost of materials, operating expenses, and other income for different financial years.
This section details various financial line items for J Infratech Limited, including changes in property held as stock, employee benefits expenses, finance costs, depreciation and amortization, other expenses, tax expenses, and deferred tax movements. It also provides information on revenue recognition from contracts with customers, including disaggregation by type, geography, and timing, along with details on contract balances and reconciliation of revenue.
This section details various financial disclosures, including service concession arrangements, contingent liabilities, employee benefit obligations, and fair value measurements for financial instruments. It provides information on project milestones for certain concessions, details regarding disputed tax liabilities, and outlines the accounting for defined benefit plans, including actuarial assumptions and sensitivity analysis. Furthermore, it presents a breakdown of financial assets and liabilities categorized by their fair value hierarchy.
This section details the financial position of J Infratech Limited as of March 31, 2024, and projections for March 31, 2025, and March 31, 2026, covering financial assets, liabilities, and liquidity risk management. The data includes carrying values and fair values for various items, such as trade receivables, cash, borrowings, and lease liabilities. The company employs various risk management frameworks, including credit risk, liquidity risk, and market risk, and monitors these risks through various analyses.
This section details various financial and related party disclosures for J Infratech Limited, including profit changes, CSR expenditure, related party transactions, and balances of trade receivables, payables, and investments. It outlines the structure of related parties, including subsidiaries, joint ventures, and key managerial personnel, along with details on rent expenses, remuneration, professional charges, purchases, revenue from operations, salary expenses, and various balances such as trade receivables and contract liabilities.
This section details various transactions eliminated and balances eliminated between J Infratech Limited and related parties, including Hamirpur Byepass Private Limited and Jandu Silchar Highway Private Limited, for different reporting periods. It also lists balances eliminated as of March 31, 2026, and presents the balance sheet components as of March 31, 2025, alongside various asset and liability figures as of March 31, 2026. The text also provides context on the first-time adoption of Indian Accounting Standards (Ind-AS) and the application of various accounting standards.
This section presents a snapshot of the company's financial position, detailing current assets, total assets, and related components. The figures provided include various components such as current assets, total assets, and their respective changes or related figures, with amounts stated in Indian million except for share data.
This section details the restated consolidated financial information for J Infratech Limited as of March 31, 2024, presenting a breakdown of equity and liabilities. The data includes various components such as borrowings, lease liabilities, provisions, and tax liabilities, leading to total equity and liabilities figures. The balance sheet also shows detailed breakdowns of non-current and current assets, including property, plant and equipment, investments, and cash equivalents, culminating in total assets and equity.
This section details the restatement of financial information from previous GAAP to Indian Accounting Standards (Ind AS). It includes various adjustments related to income, expenses, tax, and equity, covering aspects such as revenue recognition, lease accounting, financial instrument recognition, and the treatment of various assets and liabilities. The text also outlines the group's application of optional and mandatory exemptions under Ind AS during the transition period.
The financial statements pertain to J Infratech Limited, which is primarily engaged in road construction and allied infrastructure activities. The company has a single operating segment, and revenue and non-current assets are attributable to India. The document details various ownership interests in subsidiaries and joint ventures, including the breakdown of these interests as of March 31, 2026, 2025, and 2024. Furthermore, it mentions business combinations, subsequent events related to GST proceedings in Assam, and the recognition of contingent liabilities.
This section details various restated adjustments and reconciliations between audited and restated financial statements for different periods. It includes adjustments related to audit qualifications, prior period items, and the impact of these adjustments on total equity and net profit after tax. Furthermore, the text provides details on quarterly returns, statutory dues, and various CARO provisions concerning related party disclosures, inventory verification, and property, plant, and equipment records.
This section provides management's discussion and analysis of the financial condition and operations of the company. It clarifies that certain non-GAAP financial and operational measures are included, and warns that they may not be comparable across the industry. The company describes itself as an integrated infrastructure engineering, procurement, and construction player focused on roads, highways, and bridges. The text details the company's project execution capabilities, workforce, and the scope of its ongoing and completed projects across various states in India.
This section provides details on the company's order book, customer relationships, and financial performance across fiscal years. The order book showed a decline from FY2024 to FY2026, while revenue from operations grew significantly. Key financial metrics such as EBITDA margin and Return on Equity (RoE) are provided, alongside various working capital and debt ratios.
This section details various financial calculations and significant factors impacting the company's operations and financial condition. It outlines specific methodologies for calculating key financial metrics such as Total Borrowings, Debt-Equity Ratio, Net Debt, various days metrics, and returns on equity and capital employed. Furthermore, it discusses dependencies on government contracts, the geographical concentration of the order book, and risks associated with project execution, adverse weather conditions, and fluctuations in the cost of construction materials.
This section primarily discusses various risks and considerations related to the company's operations, financing, and market environment. It highlights potential financial losses due to cost overruns, interest rate fluctuations, and execution risks inherent in the development and construction industry. The text also details dependencies on government contracts, competition from other infrastructure companies, and the impact of macroeconomic factors on the sector.
This section details various accounting treatments and recognition criteria for different financial statement line items, including revenue recognition, contract accounting, and asset classifications under Indian Accounting Standards (Ind AS). It outlines principles for classifying liabilities, defining revenue recognition for various contracts (like EPC and service concessions), and specifying how to account for contract balances, variable consideration, and various asset classes such as Property, Plant and Equipment (PPE), Intangible Assets, and Investment Property. The text also covers impairment testing procedures for non-financial assets and investments in joint ventures.
This section details various accounting treatments and recognition criteria for different financial statement line items and instruments according to Indian Accounting Standards (Ind AS). It covers impairment testing for financial assets, inventory valuation methods, initial recognition and subsequent measurement of financial assets and liabilities, classification of financial instruments, treatment of cash, earnings per share calculation, tax recognition, employee benefits, provisions, and borrowing costs. It also outlines rules for leases, commitments, and the consolidation of subsidiaries and joint ventures.
This section details various accounting treatments and financial data presented in the Restated Consolidated Financial Information, covering aspects such as cost recognition, liabilities, financial guarantees, operating segments, and subsequent events. It provides a comparative overview of key financial figures across Fiscal 2026, Fiscal 2025, and Fiscal 2024, highlighting changes in revenue components, operating expenses, and income streams.
This section details various changes in income, expenses, and operational activities across fiscal years, highlighting significant growth in certain areas. Total expenses increased substantially, primarily driven by higher costs for materials and construction/operating expenses. Revenue from operations showed strong growth, with construction and project-related activities forming the largest component. Furthermore, there were notable changes in revenue from toll receipts and other income streams, alongside adjustments related to inventory and working capital.
This section details various financial statement line items and cash flow movements across Fiscal 2024 and Fiscal 2025, highlighting changes in expenses, profits, and cash flows. Key observations include increases in certain costs and depreciation, alongside significant growth in restated profit before tax and profit for the year. The cash flow data provides a breakdown of operating, investing, and financing activities for the respective fiscal years.
This section details various cash flow movements, profit figures, and contingent liabilities for different fiscal years. Key operating cash flows for Fiscal 2024 and 2024 were reported, along with restated profit before tax figures adjusted for various expenses and incomes. The text also outlines net cash flows from investing and financing activities for Fiscal 2026, 2025, and 2024, detailing payments for assets and borrowings. Furthermore, contingent liabilities as of March 31, 2026, are disclosed, including disputed tax liabilities and a GST matter.
This section details various observations and responses from statutory auditors across different fiscal years, covering aspects such as statutory dues, fixed asset records, inventory verification, and related party transactions. Auditors have generally found compliance, with some noting areas for improvement, such as strengthening monitoring mechanisms for statutory payments and completing the implementation of site-wise fixed asset registers. Disputed statutory dues were noted, with some amounts deposited against orders, and management has provided explanations regarding these matters. Furthermore, observations related to the maintenance of detailed fixed asset records and the segregation of segment-wise financial statements were addressed by management through various implementation and strengthening processes.
This section details various observations and responses from statutory auditors regarding financial statements and internal controls for the company and its subsidiaries. Observations covered issues related to inventory records, statutory dues, loan documentation, internal audit systems, and cash losses for different fiscal years. Management provided responses indicating that procedures were strengthened or that discrepancies were already accounted for in the financial statements, with no modifications to the statutory audit opinions in most cases. Additionally, this section mentions recent developments including letters of acceptance for integrated resource management projects and the incorporation of subsidiaries for government-awarded projects.
This section details the capitalization structure and outstanding borrowings of the company as of March 31, 2026, and a summary of aggregate outstanding borrowings as of August 31, 2026. The capitalization data includes current and non-current borrowings, total borrowings, equity share capital, and total equity, along with derived ratios comparing borrowings to equity. The financial indebtedness section summarizes various loan facilities, including fund-based and non-fund-based borrowings, detailing sanctioned amounts versus outstanding amounts. It also outlines various terms related to these borrowings, such as tenor, interest rates, security requirements, repayment terms, and events of default.
Key points (475, showing 60)
The independent auditor examined the restated consolidated financial information of J Infratech Limited, including the restated consolidated statement of assets and liabilities as at March 31, 2026, March 31, 2025, and March 31, 2024. p.323
The independent auditor examined the restated consolidated statement of profit and loss, including other comprehensive income, for the financial years ended March 31, 2026, March 31, 2025, and March 31, 2024. p.323
The Company's management is responsible for the preparation of the Restated Consolidated Financial Information for inclusion in the DRHP. p.325
The Board of Directors and Management of the Company are responsible for the compilation, preparation and approval of the Restated Consolidated Financial Information. p.325
The Restated Consolidated Financial Information was compiled from audited consolidated financial statements of the Group as at and for the financial year ended March 31, 2026. p.326
Special purpose consolidated financial statements of the Group were prepared for the financial years ended March 31, 2025 and March 31, 2024. p.326
Financial information for the financial years ended March 31, 2025 and March 31, 2024 was prepared after incorporating necessary adjustments to align recognition and measurement principles with Ind AS for the financial year ended March 31, 2026. p.326
Financial information for the financial years ended March 31, 2025, and March 31, 2024, included in the Audited Special Purpose Financial Statements was derived from Audited Indian GAAP Financial Statements and financial statements of Historical Subsidiaries and joint ventures. p.327
The Previous Auditor reported that the Prior Period Restated Consolidated Financial Information had been prepared after incorporating adjustments for changes in accounting policies, material errors and regrouping/reclassifications retrospectively for the financial years ended March 31, 2025 and March 31, 2024. p.328
The financial information of Hamirpur Byepass Private Limited included total assets of ₹230.09 Crore as at March 31, 2025, total revenue from operations of ₹224.53 Crore and profit after tax of ₹23.77 Crore. p.330
The financial information of Jandu Silchar Highway Private Limited amounted to ₹4.44 Crore, ₹1.23 Crore and ₹ (62.76) million for the financial year ended March 31, 2025. p.330
The Group's share of profit/(loss) in respect to twelve joint ventures considered in the Consolidated Financial Statements amounted to ₹1.37 Crore. p.331
Audit report on Standalone Financial Statements (Indian GAAP) for the financial year ended March 31, 2025, was provided by Mohit Bharti & Associates. p.333
Examination report on Restated Consolidated Financial Information for financial years ended March 31, 2025 and March 31, 2024, was provided by Mohit Bharti & Associates. p.334
Audit report on Special Purpose Consolidated Financial Statements for the financial year ended March 31, 2025, was provided by Mohit Bharti & Associates. p.334
Audit report on Financial Statements for Jandu Silchar Highway Private Limited for the financial year ended March 31, 2026, was provided by H. K. Agrawala & Associates. p.335
Audit Report on Financial Statements for the financial year ended March 31, 2026 for JIL Azvirt JV was provided by Mohit Bharti & Associates. p.337
Audit Report on Financial Statements for the financial year ended March 31, 2025 for Ram Kumar Jandu JV was provided by Mohit Bharti & Associates. p.339
Revenue from operations for FY24 was ₹1,411.21 Crore p.342
Restated Profit for the year for FY24 was ₹85.93 Crore p.342
Restated Profit before tax for FY26 was ₹331.68 Crore p.343
Operating profit before working capital changes for FY26 was ₹423.89 Crore p.343
Net cash flows from operating activities for FY26 were ₹161.93 Crore p.343
Cash flows from investing activities for FY26 were Rs. (1,408.40) million p.343
Proceeds from long term borrowings for FY26 was ₹170.04 Crore p.343
Issued, subscribed and fully paid up capital as of March 31, 2026 was ₹116.99 Crore p.344
Balance as at March 31, 2026 for Other equity (Reserve and surplus) was ₹474.63 Crore p.344
Transfers between financial statement levels are recognized at the end of the reporting year in which the change occurs. p.347
Consolidation of a subsidiary commences from the date control is obtained and ceases when control is lost. p.347
Intra-group assets, liabilities, income, expenses, cash flows and unrealised gains and losses arising from intra-group transactions are eliminated in full on consolidation, except to the extent a loss provides evidence of impairment. p.347
Investments in joint ventures accounted for using the equity method are presented as a separate line item in the Restated Consolidated Statement of Assets and Liabilities and are not classified as financial assets for presentation purposes. p.348
A contract asset represents the Group's right to consideration in exchange for goods or services transferred to a customer when that right is conditional on something other than the passage of time. p.348
A contract liability represents consideration received, or an amount due, from a customer before the Group transfers the related goods or services. p.348
Revenue from contracts with customers is recognised when or as control of the promised goods or services is transferred to the customer at an amount that reflects the consideration to which the Group expects to be entitled. p.349
Variable consideration is estimated using the expected-value method or the most-likely-amount method, whichever better predicts the consideration to which the Group will be entitled, and is included only to the extent that it is highly probable that a significant reversal of cumulative revenue recognised will not occur when the uncertainty is subsequently resolved. p.349
The Group derives revenue principally from EPC construction contracts, construction and operation services under HAM service concession arrangements, operation and maintenance ("O&M") and other service contracts, toll management / collection arrangements, and sale / transfer of land or development rights under development arrangements. p.349
Revenue is recognised over time for EPC contracts when the relevant performance obligation satisfies the criteria for over-time recognition, including where the Group's performance creates or enhances an asset that the customer controls as it is created or enhanced or, where applicable, the asset being created has no alternative use to the Group and the Group has an enforceable right to payment for performance completed to date. p.350
Contract revenue recognised in excess of amounts billed is presented as a contract asset. p.350
Amounts billed or consideration received in advance of the related performance are presented as contract liabilities. p.350
A receivable is recognised when the Group's right to consideration is unconditional and only the passage of time is required before payment is due. p.350
Contract modifications are accounted for as a separate contract when the scope increases because of the addition of distinct goods or services and the price increase reflects their stand-alone selling prices. p.351
Incremental costs of obtaining a contract are recognised as an asset when the Group expects to recover those costs, unless the practical expedient for costs that would otherwise be amortised over one year or less is applied. p.351
Revenue from construction or upgrade services under HAM arrangements is recognised over time as the Group's performance creates or enhances infrastructure controlled by the grantor. p.351
Consideration for construction services is measured in accordance with Ind AS 115 having regard to the stand-alone selling price of the construction services, including an appropriate construction margin where supported by the arrangement and underlying estimates. p.351
Finance income on the HAM financial asset is recognised using the effective interest rate ("EIR") method on the outstanding carrying amount of the financial asset. p.351
Finance income arising from the HAM financial asset is presented as part of revenue from operations where it arises from the Group's ordinary service concession activities. p.351
Revenue from O&M services is recognised over time as the related services are rendered. p.351
Revenue from toll management / collection arrangements is presented on a gross or net basis depending on whether the Group acts as principal or agent in the relevant arrangement. p.351
Where the Group is the principal, toll / user-fee collections are recognised as revenue on a gross basis and the corresponding contractual fee, premium or amount payable to NHAI / NHIDCL or another authority is recognised separately as an expense. p.351
Where the Group acts as an agent and does not control the specified service before transfer, only the fee or commission to which the Group is entitled is recognised as revenue. p.351
Revenue is recognised when or as the relevant performance obligation is satisfied and control of the promised land / development rights is transferred to the customer, having regard to contractual conditions, possession, enforceable rights and other relevant facts and circumstances. p.351
Variable and non-cash consideration, if any, arising under such development arrangements is measured in accordance with Ind AS 115 and is subject to the constraint on variable consideration. p.351
Costs of land / development rights are recognised in accordance with the Group's inventory policy and expensed when the related revenue is recognised, as applicable. p.351
Interest income, other than finance income on HAM financial assets, is recognised using the EIR method in accordance with Ind AS 109. p.352
Dividend income is recognised when the Group's right to receive payment is established. p.352
What could go wrong, per the company
Risk factors
The risks the company is legally required to disclose, in its own words.
An investment in the company involves a high degree of risk, and unforeseen uncertainties may impair the business, financial condition, and cash flows. The company's business heavily relies on contracts awarded by various Government Entities, and adverse changes in government policies or market conditions could lead to contract foreclosures or renegotiations. Furthermore, a significant portion of revenue is dependent on a few key customers, creating concentration risk. The execution of projects, particularly EPC projects, is crucial, and there is a risk of delays or cost overruns due to various factors.
The company faces various risks that could negatively impact its financial condition and operational results. These risks include exposure to natural or man-made disasters, geopolitical tensions, and civil unrest that could affect financial markets and business operations. Risks are also present concerning the funding and annuity payments for HAM projects, where delays or disputes could harm financial health. Furthermore, securing new EPC and HAM projects is uncertain, and the company may face difficulties in bidding due to competitive factors. There is also a risk related to the concentration of the Order Book and revenue in specific states, exposing the company to regional economic, regulatory, and political changes. Finally, various implementation risks, such as construction delays, material shortages, regulatory hurdles, and potential for cost overruns, are inherent to their projects.
The company faces risks related to liquidated damages under agreements, which could lead to the deduction of costs from payments due by Government Entities. There is a risk that project termination due to delays or accidents might result in partial payments, potentially falling short of estimated cash flows. The business is heavily reliant on road and infrastructure projects awarded by Government Entities, making it vulnerable to adverse changes in budgetary allocations or government policies. Furthermore, the company has significant working capital requirements, and there is a risk that inability to generate sufficient cash flow could impact operations. The company is also entering new business ventures, such as integrated resource management, which carry risks related to successful execution and profitability.
The company faces several risks related to its financial stability, primarily concerning the timing mismatch between expenditures and payments from government entities, which strains cash flows. There are also risks associated with its manpower-intensive nature, including potential labor disputes, wage demands, and changes in labor regulations. Furthermore, the company is exposed to risks from raw material price fluctuations, potential supply shortages, and difficulties in passing on increased costs to customers. Operational risks such as accidents, equipment failure, and natural disasters pose threats to business continuity and financial performance. Finally, there are concerns regarding potential conflicts of interest due to related party transactions and the reliance on joint venture partners for bidding and execution of large projects.
The company faces several risks related to its joint venture partners, including potential disagreements over business and operations, and the possibility that partners may have conflicting economic or business interests. Contracts with Government Entities carry risks such as unfavorable terms, premature termination, and the inability to negotiate favorable terms, which could materially impact financial results. Furthermore, business operations are susceptible to seasonal, climatic, and other variations, which can cause delays or disruptions to projects. Financing agreements impose restrictive covenants that limit operational flexibility, and there is a risk that lenders may accelerate repayment schedules if covenants are breached. The company also faces risks related to the availability and fluctuation of construction equipment, and potential disruptions from public opposition or political events.
This section outlines several material risks for the company, primarily revolving around regulatory compliance, operational dependencies, and business environment challenges. Key risks include the potential for interruptions due to issues with statutory permits and approvals, reliance on subcontractors who may fail in their duties, and exposure to various liabilities from these third parties. The company faces ongoing litigation with a subcontractor, and there is a general risk of incurring additional costs or facing claims. Furthermore, risks exist concerning related party transactions, where the company cannot guarantee favorable terms. The company's brand reputation is critical, as negative publicity can harm its standing. The company operates in a competitive industry where failure to compete could lead to customer loss. Finally, there are concerns about the ability to execute growth strategies due to resource constraints and market uncertainties.
The company faces risks related to its physical premises, including potential lease or license terminations that could force relocation or result in unfavorable new terms. The success of the business is highly dependent on the ability to meet evolving customer requirements, and failure to do so could negatively impact cash flow and operations. Market conditions pose risks to expected profit margins, and infrastructure projects carry various risks such as land acquisition, construction, financing, and commodity price fluctuations. Furthermore, there are concerns regarding the lack of experience among directors in listed companies, which might challenge compliance with SEBI regulations. The company also faces risks related to intellectual property protection, including the potential for infringement or misappropriation of its brand name, which could necessitate costly rebranding efforts. Finally, there are significant risks associated with internal controls, anti-corruption laws, and the potential for penalties if these measures are inadequate.
The company faces risks related to non-compliance with statutory dues, which may negatively impact operations and financial condition. There are concerns regarding the potential for future legal proceedings or regulatory actions due to past payment delays. Furthermore, the company is exposed to risks from the obsolescence, theft, destruction, or breakdown of its equipment, which could lead to project delays and cost overruns. The business heavily relies on Information Technology systems, and there is a risk of failure or disruption to these systems. Finally, the company's ability to pay dividends in the future is uncertain due to various financial and external factors.
The company faces risks related to the discontinuation or modification of terms by key software providers, which could disrupt operations and lead to losses in information or production. There is also a risk of data security breaches compromising confidential information or personal data of employees. Compliance with environmental, health, and safety laws in India poses a risk of increased liabilities, potential operational curtailment, or penalties. Furthermore, there is a risk that stringent environmental laws may increase liabilities or require additional capital expenditure. The success of operations is heavily dependent on the retention of Key Managerial Personnel and senior management, and the inability to attract or retain such personnel could negatively impact the business. The company also faces risks related to the control exerted by its Promoters and Promoter Group over major company decisions and potential conflicts of interest. Finally, the reliance on industry reports may introduce inaccuracies, as the data is based on estimates and assumptions that may change.
This section outlines various risk factors for the company, primarily concerning the evolving legal and regulatory environment in India. Risks include potential changes in laws, new compliance burdens from various codes and tax laws, and uncertainty regarding the interpretation of these laws. The business is also vulnerable to macroeconomic factors, such as global economic slowdowns and trade disruptions. Furthermore, the company's reliance on the roads and infrastructure sector exposes it to industry-specific challenges like delays and competition. Risks related to natural disasters, geopolitical tensions, and market conduct, such as competition laws, are also highlighted. Finally, risks associated with the listing of equity shares include potential market surveillance and uncertainty regarding the actual trading market post-listing.
This section outlines various risks related to trading, legal enforceability, and financial reporting for investors. Risks include market volatility influenced by various factors, limitations on enforcing foreign court judgments in India, and potential issues with the timing or ability to list and trade equity shares. Furthermore, the section details complexities regarding shareholder rights under Indian law, the uncertainty of listing timelines, tax implications on capital gains, currency exchange risks, and potential dilution from future equity issuances. Finally, it addresses the differences between various accounting standards and investment restrictions concerning foreign investors.
The text outlines various restrictions related to the withdrawal of bids by different investor categories after a bid/offer closing date, depending on their investor type. It also discusses potential events that could affect investor decisions between bid submission and allotment, such as changes in monetary policy or economic conditions. Furthermore, it details legal provisions that might prevent third parties from acquiring control of the company post-offer and the ability of existing shareholders to exercise pre-emptive rights regarding new equity issuance.
The provided text details various financial statements, including profit and loss, changes in equity, and cash flows for the years ending March 31, 2024, 2025, and 2026. It also summarizes contingent liabilities and related party transactions. The contingent liabilities section highlights pending tax claims and ongoing GST matters, including deposits made under protest and subsequent orders from the GST Department, which the company is evaluating for legal recourse.
This section details various related party transactions, including remuneration, fees, and revenue sharing with promoters, directors, and other entities. The data covers transactions across fiscal years 2026, 2025, and 2024, showing the percentage of revenue derived from operations. Several transactions involve directors' wives, joint ventures, and various forms of payments such as rent, remuneration, and sub-contract expenses. The data also includes interest received and repayment/part payment for loans and property transactions.
Key points (184, showing 60)
The business is primarily dependent on contracts awarded by the Government of India (GoI) or state governments. p.26
Adverse changes in the policies of central or state or local authorities and market conditions, including political and economic events, may lead to contracts being foreclosed, terminated, restructured, or renegotiated, resulting in a decline in revenues. p.27
The business is primarily dependent on contracts awarded by specific Government Entities such as NHIDCL, NHAI, MoRTH, BRO, PWD, and Indian Railways. p.27
Loss of, or reduction in business from, such customers will have a significant adverse impact on the business and results of operations. p.29
Majority of revenue from operations is derived from the top two customers, which account for a significant percentage of revenue. p.29
Loss of, or reduction in business from, any of these key customers could have a significant adverse impact on cash flows and financial condition. p.29
Adverse changes in the policies adopted by the government regarding the award of its projects could adversely affect the ability to secure new contracts or continue ongoing projects. p.29
The revenue from execution of EPC projects and HAM projects constitutes a significant portion of the Revenue from Operations. p.30
There can be no assurance that there will not be any reduction in the EPC projects allocated to the company, which could significantly impact future revenues. p.30
Any increase in input costs, adverse site conditions, or disruptions in supply chains may result in cost overruns or delays in contracts, which may not be fully recoverable from Government Entities. p.30
The ability to negotiate the terms of contracts is limited, and such terms are often in favor of the government and government-owned customers. p.30
Natural or man-made disasters, hostilities, wars, geopolitical tensions, terrorist attacks, civil unrest, and other acts of violence could adversely affect the financial markets and the business. p.31
HAM projects are awarded on an annuity basis, which may expose the company to cost overruns due to increases in input prices. p.31
Significant upfront funding is required for HAM projects, and delays or inability to achieve timely financial closure could affect execution timelines. p.31
Cash flows from HAM projects depend on periodic annuity payments from relevant authorities, and delays, disputes, or defaults in these payments could negatively affect the financial condition and operations. p.31
The company may be required to make equity contributions towards HAM projects, and inability to meet such funding or delay in arranging it could delay implementation, increase financing costs, affect revenue realization, and adversely affect the business. p.31
The business, growth prospects, and financial performance depend on the ability to continuously secure new EPC and HAM projects, with no assurance of procuring new projects. p.31
Projects are awarded primarily through a competitive bidding process, and there is no assurance that bids will be accepted. p.31
The company may not always meet the bid requirements of track-record or technical and financial specifications for certain projects. p.31
The company may not win every EPC contract tender bid due to competitors offering better pricing, experience, track record, technical expertise, financing capabilities, or guarantees. p.31
The Bid to Win Ratio for EPC projects and HAM projects shows that the company may not be able to continue receiving such projects or achieve higher project values based on technical qualifications and financial scores. p.31
If the company cannot partner with other companies or lacks credentials to be the partner-of-choice, it may lose opportunities to bid for large EPC projects and HAM projects, affecting growth plans. p.32
Undertaking new projects requires obtaining consents from relevant authorities, other regulatory authorities, and sometimes lenders. p.32
The tender processes conducted by Government Entities may be subject to changes in qualification criteria, unexpected delays, and uncertainties. p.32
Projects awarded to the company may be subject to litigation by unsuccessful bidders. p.32
Revenue from Operations is geographically concentrated in Assam, Maharashtra, and Gujarat during the last three fiscal years. p.33
A significant portion of future revenue and financial performance is dependent on the ability to execute and complete projects in Telangana and Assam in a timely manner and on the ability to receive payments for such projects. p.33
Adverse developments affecting the state of Telangana and Assam, such as changes in regulatory or governmental policies, economic conditions, or availability of resources, could adversely affect order inflows and revenue recognition. p.33
Political or security-related developments in Telangana and Assam could adversely affect the business, financial condition, results of operations, and prospects. p.33
Project delays, modifications in scope, or cancellations may occur due to delays in payments by Government Entities or company defaults, incidents of force majeure, adverse cash flows, regulatory delays, or other factors beyond control, which can affect the Order Book. p.34
The termination of a contract by a former joint venture partner on national security grounds resulted in a reduction in the Order Book. p.34
Government Entities may terminate contracts or default on payments due to unforeseen circumstances such as failure to obtain approvals or rights over land, public interest litigations, or disputes with environmental activists. p.34
Liquidated damages are stipulated under relevant agreements and may lead to the encashment and appropriation of bank guarantees or performance security. p.36
In the event of termination due to delays or accidents, partial payments may be received, which could be less than estimated cash flows. p.36
A previous instance of contract termination arose due to the relevant authority's failure to provide hindrance-free access to the project site and delays in removing hindrances. p.36
Delays in the completion of development may result in cost overruns, lower or no returns on capital, and reduced revenue for the customer, impacting project performance. p.36
The business largely comprises road and infrastructure projects in India undertaken or awarded by Governmental Entities. p.36
The loss of contracts, particularly road and infrastructure projects, may have a material and adverse effect on the business and financial results. p.36
There is no assurance that the Government will continue to emphasize the road and infrastructure projects construction sector or related sectors. p.36
Adverse changes in budgetary allocations for infrastructure development or a downturn in available work in the roads and infrastructure projects sector could adversely affect business prospects and financial performance. p.36
The concentration of the business in the road infrastructure vertical exposes the company to risks such as slowdown in construction activities or reduction in commissioned projects. p.37
Existing and potential competitors in the road and infrastructure projects may increase their focus, potentially reducing market share. p.37
The company has significant working capital requirements, and inability to generate sufficient cash flow to meet them may adversely affect results of operations. p.37
Substantial working capital is required to finance raw material purchases and EPC projects prior to receiving payments from Government Entities. p.37
Working capital requirements may increase if payment terms do not provide for advance payments or if payment schedules are structured to receive payments towards later stages of a project. p.37
The company expects an incremental working capital gap during Fiscal 2027, which is proposed to be funded in part from the Objects of the Offer. p.37
Inability to arrange bank guarantees or insurance surety bonds may adversely affect cash flow and financial condition. p.37
Inability to finance working capital requirements due to changes in geopolitical situations, tariff regulations, interest rates, insurance, or borrowing/lending restrictions may adversely affect the ability to secure financing. p.37
The company has entered into new business ventures, such as integrated resource management, requiring the development and operationalization of necessary execution ecosystems and logistics arrangements. p.38
The ability to derive revenues from the new integrated resource management venture depends on the ability to timely operationalize the business and manage pricing, logistics, and compliance requirements. p.38
There is no assurance that the new business initiative will be successful, profitable, or scalable, or that expected commercial benefits will be realized within the anticipated time period. p.38
Diversification efforts may require significant investment in resources, development of new technical capabilities, and compliance with additional regulatory requirements. p.38
Diversification efforts may result in delays, increased costs, and diminished quality if operational systems and controls are not implemented or managed efficiently. p.39
Actual cost of executing projects may vary substantially from bid assumptions due to unanticipated increases in construction material costs, fuel, labor, or other inputs. p.39
Actual expense in executing a project may vary substantially due to the inability of the customer to obtain requisite no objection certificates, resulting in delays and increased costs. p.39
Unanticipated increases in raw material costs due to geopolitical developments or other market conditions may have compounding effects on project costs. p.39
Ability to pass on increases in raw material costs to customers may be limited in contracts with limited or no price escalation provisions. p.39
Other risks inherent to the development and construction industry may result in profits being less than estimated or lead to losses due to cost and time overruns. p.39
Outstanding legal proceedings exist against the Company, Directors, Promoters, Key Managerial Personnel, and Senior Management, which may negatively affect business and financial condition. p.40
Litigation or arbitration could result in substantial costs and a diversion of effort or subject the company to significant liabilities to third parties. p.40
Litigation and regulatory matters
Litigation
Court cases, tax disputes and regulatory proceedings involving the company, promoters and directors.
The section outlines the company's policy regarding outstanding litigation, including monetary and subjective thresholds for disclosure. It clarifies that certain proceedings, such as civil and arbitration claims, are considered material if the monetary amount exceeds specific percentages of turnover, net worth, or profit/loss. It also details criteria for tax matters and pre-litigation notices. Furthermore, the section details material dues to creditors, setting a threshold for disclosure based on a percentage of trade payables.
The section details various aspects related to the company's financial standing, regulatory compliance, and pending approvals. It discloses the existence of material creditors, the status of various consents, licenses, and registrations required for business operations, and a list of material approvals that are pending or have not been obtained. Furthermore, it mentions an issue regarding the inability to submit an application for registration under the Inter-State Migrant Workmen Act due to technical issues on the Shram Suvidha Portal.
The company reviewed companies for group company identification based on a Board resolution and SEBI ICDR Regulations. The criteria included related party transactions under Ind AS 24 and other companies deemed material by the Board according to the Materiality Policy. The criteria for material companies involved transactions with the company during the most recent financial year that exceeded 10% of the total consolidated Revenue from Operations.
Key points (20)
There are no outstanding criminal proceedings. p.471
There are no outstanding actions by regulatory authorities and statutory authorities against Key Managerial Personnel and Senior Management. p.471
A reference petition was filed by Geosys India Infrastructures Limited against the Company concerning non-payment of dues and wrongful retention of machinery, involving amounts up to ₹10.17 Crore and ₹8.40 Crore. p.472
A show cause notice was issued by the CGST Audit – Commissionerate, Nagpur alleging failure to pay and report goods and service tax for a period spanning April 2020 to March 2023, with dues amounting to ₹12.85 Crore and interest of ₹3.70 Lakh. p.472
The Company has filed a complaint against Kedareshwar Infrastructure Developers Private Limited and others under the Negotiable Instruments Act, alleging dishonored cheques. p.473
A forest offence report was filed against Hari Niwas alleging illegal installation of electric tower poles and illegal possession of land on forest land. p.473
A complaint was instituted and a summon order was issued against the Company by the Haryana State Pollution Control Board alleging operation of a hot mix plant without obtaining necessary consents. p.473
Outstanding dues to creditors were considered material if the amount due exceeded 5% of the restated consolidated total trade payables as of March 31, 2026. p.475
Micro, Small and Medium Enterprises creditors accounted for ₹7.57 Crore out of the total outstanding dues. p.475
The Company has three material creditors with an outstanding amount of ₹29.82 Crore as of March 31, 2026. p.476
The Company has obtained various Material Approvals pertaining to ongoing EPC Projects, including consents to establish and operate from various state Pollution Control Boards under the Water (Prevention and Control of Pollution) Act, 1974, and Air (Prevention and Control of Pollution) Act, 1981. p.477
The Company has obtained various Material Approvals related to its business and operations, which comprise engineering, procurement and construction (EPC) and hybrid annuity model (HAM) projects. p.477
The Company has obtained various Tax related approvals, including a permanent account number from the Income Tax Department, Goods and Services Tax registration certificates from the Government of India in 13 states and three union territories, and various registration certificates under Professions, Trades, Callings and Employment Acts in four states. p.478
The Material Subsidiaries have obtained various Tax related approvals, including permanent account numbers from the Income Tax Department, Goods and Services Tax registrations, and Legal Entity Identifiers. p.478
The Company has obtained various Labor and employee related approvals, including registration under the Punjab Shops and Commercial Establishments Act, 1958, and registration under the Employees’ Provident Funds and Miscellaneous Provisions Act, 1952. p.479
The Material Subsidiaries have obtained various Labor and employee related approvals, including registration under the Employees’ State Insurance Act, 1948, the Contract Labour (Regulation and Abolition) Act, 1970, and the Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996. p.479
There are pending Material Approvals for the registration under the Contract Labour (Regulation and Abolition) Act, 1970 for Hubli, Silchar EPC Pkg 2, and Panchgram projects. p.479
The Company has not been able to submit its application for registration under the Inter-State Migrant Workmen (Regulation of Employment and Conditions of Service) Act, 1979 due to technical issues on the Shram Suvidha Portal 2.0. p.479
The Company has made an application for obtaining a trademark registration with application number 377479425 dated January 24, 2026. p.480
The company does not have any Group Company. p.481
Regulatory disclosures
Approvals, licences, and any regulatory actions or compliance matters.
The section details various corporate and regulatory approvals related to the offer, including resolutions from the Board and Shareholders for the Offer, Fresh Issue, and the Draft Red Herring Prospectus. It also confirms that Promoter Selling Shareholders have consented to the transfer of their shares according to SEBI ICDR Regulations. Furthermore, the company has received in-principle listing approvals from BSE and NSE, and confirms compliance with the Companies (Significant Beneficial Owners) Rules, 2018. The text also outlines eligibility criteria regarding net tangible assets, operating profit, and net worth, and specifies conditions for compliance with SEBI ICDR Regulations and various legal requirements.
The section details various provisions related to the Red Herring Prospectus, including liability for repayment of money if not repaid within the prescribed time, and the reimbursement of expenses incurred by promoters on behalf of selling shareholders. It mandates that necessary formalities for listing and trading of Equity Shares must be completed within three working days of the Bid/Offer Closing Date. Furthermore, it outlines penalties for failing to allot Equity Shares within the stipulated timeline. The text also covers consents required from various parties and expert opinions, including those from Chartered Accountants and Independent Chartered Accountants, which must be obtained and not withdrawn.
The section details various compensation mechanisms and timelines related to investor grievances and bid processing, particularly concerning bids made through the UPI Mechanism. It outlines penalties for delays in resolving complaints and specifies compensation rates based on the bid amount and the duration of the delay. Furthermore, it discusses the process for resolving grievances, the company's estimated timeframes for redressal, and the company's commitment to comply with SEBI circulars regarding investor grievances. The text also covers the legal framework governing the offer, including the jurisdiction and the manner in which equity shares will be allotted and traded.
This section details various timelines and procedures related to the bid/offer process, including submission times for different types of bids, the handling of bid revisions, and the consequences for delays. It specifies different submission windows based on the type of investor (e.g., QIBs, RIIs, Retail Individual Investors) and the method of application (electronic vs. physical). Furthermore, it outlines conditions for the processing of bids, such as requiring funds to be blocked in an ASBA account, and details the process for handling discrepancies in bid data. The text also covers provisions regarding the revision of the price band and the potential for extensions to the bid/offer period due to various factors.
This section details the various categories of investors eligible to bid for the equity shares, including Eligible Employees, Qualified Institutional Buyers (QIBs), Non-Institutional Investors, and Retail Individual Investors. It outlines specific rules regarding the allotment of shares based on the category, including provisions for proportionate allocation, minimum bid sizes, and rules for handling under-subscription across different investor segments. The text also specifies different modes of bid processing, such as the ASBA process, and conditions related to bid amounts and payment procedures for different investor types.
This section details various procedural aspects related to the public issue offer, including the use of various bid categories, rules for investor participation, and requirements for bid forms. It outlines specific rules for allocation across different investor categories such as QIBs, Mutual Funds, Non-Institutional Investors, and Retail Individual Investors. Furthermore, it specifies requirements for investor documentation, such as PAN linking with Aadhaar, and procedures for handling applications made through the UPI mechanism. The text also covers rules regarding the blocking of funds and the redressal of investor grievances related to UPI applications.
This section details various restrictions and requirements concerning different categories of investors and bidders in the offer process, including Mutual Funds, Eligible NRIs, HUFs, Eligible Employees, FPIs, SEBI-registered funds, and various financial institutions. It outlines specific rules regarding investment limits, holding caps, documentation requirements, and how different investor types should proceed with their bids. Furthermore, it specifies conditions for handling multiple bids from certain investors and the implications of investment limits under FEMA regulations.
This section details various compliance requirements and conditions for different types of bids and participation in the Offer, categorized by the type of bidder. It outlines specific requirements for bids from insurance companies, provident funds, and various entities based on the corpus of their funds. Furthermore, it specifies rules for Anchor Investors, including minimum bid amounts and allocation reservations for different investor types. There are also detailed instructions regarding the submission of bid forms, the handling of funds through ASBA accounts, and various restrictions on bid revisions and payment methods.
This section primarily outlines various instructions and prohibitions for investors when submitting bids and applications, covering issues related to bid size, submission methods, and investor types. It details restrictions on the number of bids per account, the use of third-party bank accounts, and the timing for Qualified Institutional Buyers (QIBs) to submit bids. Furthermore, it specifies conditions for handling bid amounts, timelines for resolving issues like fund unblocking, and the responsibilities of the company and promoters regarding the offer process.
The section discusses the regulatory framework governing foreign investment in Indian securities, which is governed by the Industrial Policy, 1991, and FEMA. It details that foreign investment is permitted in certain sectors through automatic or approval routes depending on the sector. The Consolidated FDI Policy Circular consolidates previous FDI guidelines issued by the DPIIT. Furthermore, certain investments require prior government approval, especially for entities related to land borders or where the beneficial owner is a citizen of a country sharing a land border with India. The text also outlines conditions for the transfer of foreign direct investment ownership and clarifies that certain entities, like multilateral banks or funds, are not treated as entities of a particular country for investment purposes.
This section primarily outlines various provisions related to the company's share capital, including rules for amendments, the power to issue new shares, and the handling of capitalisation of profits. It details the Board's authority over share issuance and disposal, including provisions for various share classes and the treatment of different types of capital. Furthermore, the text discusses the company's ability to issue securities, the rights of lien on shares and debentures, and the procedures for dealing with the transfer and redemption of such instruments.
This section details various provisions concerning the transferability, calls, and forfeiture of shares and securities. It outlines procedures for transferring shares, including requirements for duly executed instruments, and establishes the Company's right to refuse registration of transfers under certain conditions. Furthermore, the text covers the process for making calls on unpaid amounts, the interest accrued on overdue payments, and the Board's power to forfeit shares if payments are not made as required.
This section primarily details the provisions related to the transfer, forfeiture, and management of share certificates and the conduct of shareholders' meetings. It outlines conditions under which shares can be disposed of, including provisions for forfeiture due to non-payment of calls, and procedures for issuing, modifying, or replacing share certificates. Furthermore, the text covers various aspects of General Meetings, such as notice periods, quorum requirements, and the conduct of business during these meetings. It also addresses the voting rights of members and the powers of the Chairperson in various meeting scenarios.
This section primarily outlines the procedural rules and voting rights within the Company's General Meetings and Board meetings. It details various rules concerning voting procedures, including the use of show of hands versus polls, the handling of joint holders' votes, and the requirements for proxy appointments. Furthermore, it establishes rules for the appointment, removal, and tenure of Directors, including provisions for alternate directors and the handling of director resignations. The rules also cover the powers of the Board and its committees in conducting business and making decisions.
This section primarily outlines the procedural aspects related to the Board and Directors' powers, including decision-making processes, borrowing powers, and the handling of company finances and dividends. It details the authority of the Directors to engage in various business activities, including making and signing contracts and government papers, and the delegation of such powers. Furthermore, it specifies the Board's right to make filings with governmental authorities and the general scope of powers granted to the Directors under the Articles. The section also covers provisions regarding the inspection of company accounts and the secrecy obligations of employees and officers.
This section details various agreements, resolutions, and certifications related to the company's operations and prospectuses. It includes partnership deeds, various collaboration agreements with different entities, board resolutions concerning offers and fresh issues, and various consents from auditors and other professionals to be included in the Draft Red Herring Prospectus. Furthermore, it mentions the appointment of directors and the certification of KPIs and financial aspects.
This section primarily contains declarations from various directors and officers certifying compliance with relevant laws and regulations. The declarations confirm that all statements, disclosures, and undertakings in the Draft Red Herring Prospectus adhere to the provisions of the Companies Act, 2013, and various rules and guidelines issued by the Government of India and the Securities and Exchange Board of India. Furthermore, certain individuals have confirmed the accuracy of specific statements related to themselves as a promoter selling shareholder.
The section details various term loans and financing arrangements the company has secured from different financial institutions. These include numerous term loans with varying sanction and repayment dates, interest rates, and purposes related to the purchase of construction equipment or vehicles. The financing arrangements involve different pre-payment conditions, such as percentages of the principal outstanding, and the utilization of the funds for the stated purpose.
This section details various term loans availed from different financial institutions for the purpose of purchasing construction equipment or vehicles. The loans involve different banks, varying interest rates, and distinct pre-payment conditions depending on the loan agreement. Several loans are structured with fixed monthly installments over a period spanning from 2026 to 2029, with repayment schedules varying significantly across the listed instruments.
This section details various term loans availed from Axis Bank Limited and HDFC Bank Limited for the purpose of purchasing construction equipment or vehicles. The loans involve different sanction dates, interest rates, and repayment schedules, primarily structured over a three-year period ending in May 2029. The pre-payment conditions for these loans vary, with some allowing for prepayment within 12 months for a reduced penalty, while others impose a higher penalty thereafter.
This section details various term loans availed from HDFC Bank Limited, primarily for the purpose of purchasing construction equipment or vehicles. All listed loans have a fixed interest rate of 7.50% per annum and a repayment schedule involving 37 monthly installments spanning from June 2026 to June 2029. A key feature of these loans is the pre-payment penalty structure, which involves a penalty of 4% of the principal outstanding if prepaid within 12 months of the first EMI, and 2% of the principal outstanding thereafter. All disclosed funds were utilized for the stated purpose.
This section details various term loans availed from different financial institutions, primarily HDFC Bank Limited and Axis Bank Limited, for the purpose of purchasing construction equipment or vehicles. The loans involve different sanction dates, interest rates, and repayment schedules spanning until 2029. Several loans have pre-payment penalty clauses, varying in the percentage of principal that can be prepaid within different timeframes after the first installment.
This section details various term loans obtained from different financial institutions, primarily HDFC Bank Limited, for the purpose of purchasing construction equipment or vehicles. The loans have varying sanction and renewal dates, interest rates, and repayment schedules spanning from 2026 to 2029. Some loans have fixed interest rates, while others have actual rates, and pre-payment conditions are specified based on the time frame for prepayment. Several loans are structured with 37 monthly installments.
This section details various term loans availed from HDFC Bank Limited for the purpose of purchasing construction equipment or vehicles. The loans cover a range of sanction dates, repayment schedules, and interest rates, with most loans having an actual interest rate of 8.60% per annum. All listed loans have pre-payment conditions where a penalty is applied based on whether the principal is prepaid within 12 months of the first EMI, with different penalty structures for subsequent prepayments. The loans are structured with 37 monthly installments spanning from 2024 to 2027.
This section details various term loans availed from HDFC Bank Limited for the purpose of purchasing construction equipment or vehicles. The loans were sanctioned on March 27, 2024, and are scheduled to be repaid over 37 monthly installments ending in July 2027. The interest rates for these loans vary between 3.74% and 3.91% per annum, with an actual rate of 9.00% p.a. The pre-payment penalty structure involves a fee based on the percentage of the principal outstanding depending on how quickly the loan is prepaid.
This section details various term loans availed from HDFC Bank Limited for the purpose of purchasing construction equipment or vehicles. The loans cover a range of sanction dates, repayment schedules, and interest rates, with most loans having a fixed interest rate of 9.00% per annum. The pre-payment conditions for these loans involve penalties based on the prepayment timing relative to the first EMI. All listed loans were utilized for the purpose of acquiring construction assets.
This section details various term loans availed from HDFC Bank Limited, all sanctioned on January 28, 2025, with a fixed interest rate of 8.80% per annum. All listed loans have a repayment schedule of 37 monthly instalments spanning from April 1, 2025, to April 1, 2028. The purpose of these loans was consistently for the purchase of construction equipment or vehicles. Furthermore, all these financial arrangements include pre-payment penalties, where 4% of the principal outstanding is applicable if prepaid within 12 months of the first EMI, and 2% of the principal outstanding applies thereafter. All funds were utilized for the stated purpose.
This section details various term loans availed by the company from different financial institutions, primarily HDFC Bank Limited and Axis Bank Limited. The loans were utilized for the purchase of construction equipment or vehicles. The details provided include the loan amount, interest rates, repayment schedules, and pre-payment penalty conditions for each facility.
This section details various term loans availed from Axis Bank Limited and Kotak Mahindra Bank Limited for the purpose of purchasing construction equipment or vehicles. The data includes details such as the loan amount, interest rates, repayment schedules, and pre-payment conditions. The loans span various tenure periods, with repayment schedules extending up to 2027 and 2028, and the purpose of the funds being consistently related to capital expenditure in construction machinery.
This section details various term loans availed from Kotak Mahindra Bank Limited for the purpose of purchasing construction equipment or vehicles. The data includes details such as the loan amount, interest rates, repayment schedules, and the utilization of the funds. All listed loans involve a repayment structure of 37 monthly installments spanning from 2024 to 2027 or 2028, with a pre-payment penalty of 4% of the outstanding principal. The loans were sanctioned on various dates between October 2023 and November 2024.
This section details various loan arrangements with different financial institutions, primarily involving term loans and financing for the purchase of construction equipment or vehicles. Several loans were sanctioned by Kotak Mahindra Bank Limited, with various terms and repayment schedules. Additionally, there are numerous term loans from Tata Capital Limited / Tata Motors Finance Limited, covering various periods and utilizing different interest rates and repayment structures for asset acquisition.
This section details various loan agreements with Tata Motors Finance Limited and HDB Financial Services Limited. The majority of the listed loans are Term Loans with fixed interest rates, repayment schedules, and purposes related to the purchase of construction equipment or vehicles. Several loan agreements specify pre-payment conditions, such as a percentage of the future outstanding principal or a fixed amount, for early settlement. The loans with HDB Financial Services Limited have a different interest rate and pre-payment structure concerning the principal outstanding.
This section details various term loans availed from HDB Financial Services Limited for the purpose of purchasing construction equipment or vehicles. The loans span various sanction and repayment dates, with interest rates ranging from 8.83% to 10.24% per annum. The repayment terms involve fixed monthly installments over periods extending up to 2027 or 2028. Pre-payment conditions involve penalties based on the prepayment window, with the option to repay the principal amount subject to different percentages depending on the time frame.
This section details various term loans availed from The Federal Bank Limited, covering different sanction dates and repayment schedules. The loans are primarily for the purpose of purchasing construction equipment or vehicles. The repayment terms involve fixed interest rates and various pre-payment penalties, such as a percentage of the outstanding balance being charged if the loan is prepaid within a specified timeframe. Several different loan products and tenure periods are documented.
This section details various term loans obtained from different financial institutions for the purpose of purchasing construction equipment or vehicles. The loans involve different sanction dates, interest rates, repayment schedules, and pre-payment conditions. Several loans are from The Federal Bank Limited, with various terms, while others are from Mahindra & Mahindra Financial Services Limited. There are also loans from Axis Bank Limited, which have specific conditions regarding the percentage of principal outstanding plus GST for prepayment.
This section details various term loans obtained from Axis Bank Limited and HDFC Bank Limited for the purpose of purchasing construction equipment or vehicles. The loans involve different sanction and repayment schedules, interest rates, and pre-payment penalty structures. The loans are structured with monthly installments spanning from late 2025 to late 2028 or 2029, depending on the specific loan. The repayment terms vary, including the percentage of principal outstanding that is subject to penalty if prepaid within a year.
This section details various term loans obtained from different financial institutions, primarily HDFC Bank Limited and The Federal Bank Limited, for the purpose of purchasing construction equipment or vehicles. The details provided include the type of loan, sanction dates, interest rates, repayment schedules, and pre-payment penalties. The loans are structured with fixed interest rates, with some loans having an actual rate of 7.30% per annum, while others have an actual rate of 7.75% per annum. The funds disbursed were utilized for the specified purpose.
This section details various guarantee agreements and facilities that the company, J Infratech Limited, has secured from several banks. The agreements cover different types of facilities, including cash credit, term loans, bank guarantees, and letters of credit, with varying security obligations and financial implications in case of default. The agreements involve various security measures such as hypothecation of assets, cash margins, and personal guarantees from directors and property holders. Furthermore, some facilities are related to funding for new projects in specific regions.
This section details various financial guarantees and facilities provided by different banks for the company, J Infratech Limited. The disclosures cover numerous arrangements including cash credit, term loans, and bank guarantees, spanning different periods and amounts. These facilities are secured by various means such as hypothecation of current assets, personal guarantees of directors and promoters, and various security deposits. Some facilities are tied to specific project financing, such as for infrastructure projects, and include provisions for penalties, review of facilities, and enforcement actions in case of default.
This section details various guarantee and facility agreements the company holds with different lenders, outlining the terms, security obligations, and financial implications in case of default. Several agreements involve various types of facilities such as term loans, cash credits, and bank guarantees, with different repayment schedules and security packages. Some agreements include provisions for penal interest, lien on assets, and the right of the bank or regulator to disclose the borrower's name as a defaulter.
This section details various guarantee and facility arrangements the company has undertaken with different banks. These include guarantees for cash credit, term loans, bank guarantees, and letters of credit, covering different periods and amounts. The security obligations vary, involving collateral coverage, personal guarantees of directors and promoters, and various provisions regarding default, penalties, and the enforcement of security by the banks. Some facilities are secured by first pari passu charges on current assets, while others involve various covenants and the potential for facility review or recall.
This section details various guarantee and financing arrangements involving the company, primarily with Canara Bank and HDFC Bank Limited. These include term loans, mobilization advance guarantees, and equipment loans, which involve different security obligations such as hypothecation of assets, escrow agreements, and personal guarantees from the promoters and directors. Some facilities have specific conditions regarding repayment schedules, moratorium periods, and the potential for lenders to recall funds or seize assets in case of default.
This section details several guarantees provided by the company for equipment loans. The guarantees involve various lenders, including Kotak Mahindra Bank Limited and HDFC Bank Limited, covering different periods and amounts. The facilities are primarily equipment loans secured by hypothecation, and the terms outline the borrower's obligation to make timely payments and the liability of guarantors in case of default, including the lender's right to recall the loan and sell the financed equipment.
This section details various guarantee agreements and financing arrangements the company has undertaken with different lenders. These arrangements primarily involve equipment loans secured by hypothecation, where the guarantors are jointly and severally liable for outstanding principal, interest, charges, and costs. The agreements cover different periods and involve various types of equipment, including machinery and vehicles. The financial implications in case of default include the lender's ability to enforce guarantees, declare accounts non-performing, and seize and sell the financed assets to recover dues.
This section details various equipment loans secured by the company, involving guarantees from different lenders. The agreements cover different types of equipment, including laying machines, cranes, and machinery. The terms specify that the borrower must meet monthly installment commitments, and guarantors are jointly and severally liable for all outstanding amounts. Furthermore, lenders have the right to enforce personal guarantees, declare accounts non-performing, recall loan amounts, and seize and sell the hypothecated equipment or vehicle to recover dues, including penalties.
This section details various equipment loans and guarantees provided by lenders to the company, J Infratech Limited. The disclosures cover different types of financing, including equipment loans, which involve a first and exclusive charge by way of hypothecation on the financed equipment or vehicle. The agreements specify obligations for the borrower to meet monthly installment repayments and for guarantors to be jointly and severally liable for outstanding amounts. Furthermore, the lenders retain the right to enforce personal guarantees, declare accounts non-performing, recall loan amounts, and seize and sell the hypothecated equipment or vehicle to recover dues, including penalties.
This section details various guarantee agreements and financing arrangements the company has undertaken with HDFC Bank Limited. The disclosed agreements involve equipment loans, primarily secured by hypothecation, with various lenders. These facilities cover different types of equipment, including machinery and vehicles, and outline the consequences in case of default, such as the lender's right to enforce guarantees, declare accounts non-performing, and seize and sell the financed assets.
This section details various guarantee arrangements made by the company, primarily involving HDFC Bank Limited, for the financing of equipment or vehicles. These arrangements involve first and exclusive charges by way of hypothecation on the financed assets. The agreements specify obligations for the borrower to make timely monthly installment repayments and for the guarantors to be jointly and severally liable for all outstanding principal, interest, charges, and costs. Furthermore, the lenders have the right to enforce personal guarantees, declare accounts non-performing, recall the entire loan amount, and seize and sell the hypothecated equipment or vehicle to recover dues.
This section details various guarantee agreements and financing arrangements related to the company. Several agreements involve a personal guarantee by Hari Niwas, Kuldeep Kumar, and Mohit Jandu to HDFC Bank Limited for equipment loans. These arrangements cover a period from July 1, 2024, to July 1, 2027, for amounts of ₹39.10 Lakh. The financing involves the hypothecation of equipment or vehicles, and the financial implications in case of default include the lender's right to enforce guarantees, declare accounts non-performing, and seize and sell the hypothecated assets to recover dues.
This section details various equipment loans secured by the company through hypothecation agreements with HDFC Bank Limited. The agreements cover different types of equipment, including machinery and cement silos. The terms stipulate that the borrower must meet monthly installment repayments, and the guarantors are jointly and severally liable for all outstanding amounts. Furthermore, the lender has the right to enforce personal guarantees, declare accounts non-performing, and seize and sell the hypothecated equipment to recover dues, including penalties.
This section details various equipment loans secured by the company, involving guarantees from various lenders. The disclosed agreements cover different types of equipment, including machinery and vehicles, and specify the terms for repayment and the consequences in case of default. The agreements involve first and exclusive charge by way of hypothecation on the financed assets, with guarantors being jointly and severally liable for outstanding amounts. Furthermore, the lenders retain the right to enforce personal guarantees, declare accounts non-performing, recall loan amounts, and seize and sell the hypothecated equipment to recover dues.
This section details various guarantee agreements and financing arrangements the company has undertaken with different lenders. These arrangements involve loans for equipment or vehicles, secured by hypothecation, and specify the consequences in case of default, such as the lender's right to enforce guarantees, declare accounts non-performing, and seize and sell the financed assets to recover dues. The agreements cover different periods and involve various types of equipment.
This section details various guarantee arrangements made by the company, primarily concerning equipment loans. The disclosures involve guarantees provided to the Federal Bank Limited for the repayment of principal, interest, charges, and costs related to the financing of equipment or vehicles. These arrangements involve first and exclusive charges via hypothecation on the financed assets. Furthermore, the text outlines the lender's rights in case of default, including the ability to enforce personal guarantees, declare accounts non-performing, recall loan amounts, and seize and sell the hypothecated equipment to recover dues, including applicable penal charges.
This section details various equipment loans secured by the company, involving guarantees from different lenders. The agreements cover different periods and involve various types of financing, primarily through hypothecation of equipment or vehicles. The terms outline the borrower's obligation to make timely monthly installment repayments and the liability of guarantors for outstanding amounts. Furthermore, the lenders have the right to enforce personal guarantees, declare accounts non-performing, recall loan amounts, and seize and sell the hypothecated assets to recover dues, including penalties.
This section details various loan guarantees provided by the company, primarily involving HDFC Bank Limited, for the financing of equipment or vehicles. These guarantees involve first and exclusive charges through hypothecation on the financed assets. The agreements stipulate that the borrower must meet monthly installment repayments, and the guarantors are jointly and severally liable for all outstanding amounts. Furthermore, the lenders have rights to enforce personal guarantees, declare accounts non-performing, recall loan amounts, and seize and sell the hypothecated equipment to recover dues, including penalties.
This section details various guarantee arrangements made by the company with HDFC Bank Limited for equipment loans. The arrangements involve first and exclusive charge by way of hypothecation on financed equipment or vehicles. The guarantees cover various periods, ranging from April 1, 2025 to April 1, 2028, and involve joint and several liability for guarantors concerning principal, interest, charges, and costs. In case of default, the lender has the right to enforce personal guarantees, declare accounts non-performing, recall loan amounts, and seize and sell the hypothecated equipment or vehicle to recover dues.
This section details various equipment loans and guarantees provided by different lenders to the company, J Infratech Limited. The disclosures cover different types of facilities, including equipment loans, which involve a first and exclusive charge by way of hypothecation on financed equipment or vehicles. The provisions outline the obligations of the borrower and guarantors, as well as the consequences in case of default, such as the lender's right to enforce guarantees, declare accounts non-performing, and seize and sell the hypothecated assets to recover dues.
This section details various equipment loans secured by the company through hypothecation agreements with different lenders. The agreements cover equipment such as a VOLVO PNEUMATIC TYRE ROLLER, an ESCORT KUBOTA - HYDRA CRANE, and a Trimble 3d Control system. The terms generally require the borrower to meet monthly installment commitments, and guarantors are jointly and severally liable for outstanding amounts. Lenders retain rights to enforce guarantees, declare accounts non-performing, and seize and sell the hypothecated equipment to recover dues.
This section details various equipment loans secured by the company, J Infratech Limited, from different financial institutions. The disclosed agreements involve first and exclusive charge by way of hypothecation on financed equipment or vehicles. The terms specify borrower obligations regarding monthly installment repayments and the joint and several liability of guarantors for outstanding amounts. Furthermore, the lenders retain the right to enforce personal guarantees, declare accounts non-performing, recall loan amounts, and seize and sell the hypothecated assets to recover dues, including penalties.
This section details various equipment loans secured by the company through hypothecation, involving different lenders and guarantee periods. The agreements specify obligations for the borrower to make monthly installment repayments and for guarantors to be jointly and severally liable for all outstanding amounts, including principal, interest, charges, and costs. Furthermore, the lenders retain the right to enforce personal guarantees, declare accounts non-performing, recall the entire outstanding loan amount, and seize and sell the hypothecated equipment or vehicle to recover dues, including applicable penal charges.
This section details various loan guarantees provided by the company, J Infratech Limited, to different financial institutions. The guarantees involve equipment loans secured by hypothecation, which places obligations on the borrower and guarantors regarding timely repayments and liability for outstanding amounts. In case of default, lenders have the right to enforce guarantees, declare accounts non-performing, recall loan amounts, and seize and sell the financed equipment or vehicle to recover dues, including applicable penal charges.
This section details various guarantee arrangements with Axis Bank Limited concerning equipment loans. The arrangements involve a first and exclusive charge by way of hypothecation on financed equipment or vehicles. The terms stipulate that the borrower must meet monthly installment commitments, and the guarantors are jointly and severally liable for all outstanding principal, interest, charges, and costs. Furthermore, the lender has the right to enforce the personal guarantee, declare the account non-performing, recall the entire outstanding loan amount, and seize and sell the hypothecated equipment or vehicle to recover dues, including applicable penal charges.
This section details various guarantees provided by the company for financing equipment or vehicles from different lenders. The guarantees involve different loan amounts, periods, and security obligations, primarily through hypothecation of the financed assets. The guarantees are issued to entities such as Federal Bank Limited and HDFC Bank Limited, covering various equipment and vehicle financing arrangements.
This section details various guarantee arrangements provided by the company for loans against equipment or vehicles from HDFC Bank Limited. The disclosures cover different loan amounts, guarantee periods, and the security obligations placed on the company. The agreements involve first and exclusive charge by way of hypothecation on the financed assets, and specify the liability of the borrower and guarantors for outstanding amounts. Furthermore, the lenders have rights to enforce personal guarantees, declare accounts non-performing, and seize and sell the hypothecated equipment or vehicle to recover dues.
This section details various equipment loans secured by the company, J Infratech Limited, through hypothecation. The disclosures cover guarantees provided by various lenders, including HDFC Bank Limited and YES Bank Limited, for the financing of equipment such as a Hydraulic Mobile Crane and a Hydraulic Excavator. The terms specify borrower obligations, including timely monthly installment payments, and the liability of guarantors for outstanding amounts. Furthermore, the lenders have rights to enforce personal guarantees, declare accounts non-performing, recall loan amounts, and seize and sell the hypothecated equipment to recover dues.
This section details various equipment loans secured by the company, J Infratech Limited, through hypothecation arrangements with different financial institutions. The disclosures cover the terms of the guarantees, including the loan amounts, guarantee periods, and the security obligations placed on the company. The agreements involve various types of equipment, such as hydraulic excavators, trailers, and joining kits, and outline the consequences in case of default, such as the lender's right to recall loan amounts or seize and sell the financed assets.
This section details various equipment loans secured by the company, involving guarantees from different lenders. The disclosed agreements cover facilities such as equipment loans, which involve first and exclusive charge by way of hypothecation on financed equipment or vehicles. The terms specify borrower obligations, including timely repayment commitments, and the liability of guarantors for outstanding amounts. In case of default, lenders have rights to enforce guarantees, declare accounts non-performing, recall loan amounts, and seize and sell the hypothecated assets to recover dues, including applicable penal charges.
This section details various loan guarantees and financing arrangements the company has undertaken with Axis Bank Limited. The disclosed agreements involve equipment loans secured by hypothecation, covering different types of machinery. These agreements specify the borrower's obligations regarding monthly installment repayments and the liability of guarantors for outstanding amounts. Furthermore, the agreements outline the lender's rights in case of default, including the power to enforce personal guarantees, declare accounts non-performing, recall loan amounts, and seize and sell the hypothecated equipment to recover dues.
This section details various loan guarantees provided by the company, primarily concerning the financing of equipment or vehicles through hypothecation. The disclosures outline the terms under which lenders can enforce guarantees, including the obligation for the borrower to make timely repayments and the liability of guarantors for outstanding amounts. Furthermore, it specifies the lender's rights in case of default, such as the ability to recall the entire loan amount or seize and sell the hypothecated assets to recover dues.
This section details various loan guarantees provided by the company, primarily concerning equipment financing. The disclosures cover agreements with Axis Bank Limited and HDFC Bank Limited, outlining the terms for repayment, the liability of guarantors, and the consequences in case of default. The agreements involve first and exclusive charges via hypothecation on financed equipment or vehicles.
This section details various guarantee arrangements and financing facilities secured by the company, primarily involving loans for equipment or vehicles. The disclosures cover guarantees provided by Kuldeep Kumar and Mohit Jandu to HDFC Bank Limited, spanning different periods and amounts. These facilities involve first and exclusive charge by way of hypothecation on the financed assets, with stipulations regarding monthly installment payments and the joint and several liability of guarantors for outstanding amounts. Furthermore, the text outlines the lender's rights to enforce guarantees, declare accounts non-performing, recall loan amounts, and seize and sell the hypothecated equipment or vehicle to recover dues.
This section details various guarantee agreements with HDFC Bank Limited concerning the financing of equipment or vehicles by the company. The agreements involve first and exclusive charge by way of hypothecation on the financed assets. The terms stipulate that the borrower must meet monthly installment commitments, and the guarantors are jointly and severally liable for all outstanding principal, interest, charges, and costs. Furthermore, the lender has the right to enforce the personal guarantee, declare the account non-performing, recall the entire loan amount, and seize and sell the hypothecated equipment or vehicle to recover dues, including applicable penal charges.
This section details various guarantee agreements and loan facilities granted by HDFC Bank Limited to the company, J Infratech Limited. The disclosed agreements involve equipment loans, with various terms regarding security obligations and the consequences of default. These facilities cover different equipment, including machinery and vehicles, and specify the liability of the borrower and guarantors for outstanding amounts and the lender's rights to recover dues.
This section details various loan guarantees provided by the company, primarily concerning equipment financing. The disclosed agreements involve first and exclusive charges via hypothecation on financed equipment or vehicles. The terms specify borrower obligations, including timely monthly installment payments, and the joint and several liability of guarantors for outstanding amounts. Furthermore, the lenders have rights to enforce personal guarantees, declare accounts non-performing, recall loan amounts, and seize and sell the hypothecated equipment to recover dues, including penalties.
This section details various guarantee arrangements and financing facilities secured by the company, primarily involving loans for equipment and vehicles from different lenders. The disclosures cover the terms of the guarantees, including the type of facility, the security obligation placed on the company, and the financial implications in case of default. Several agreements involve first and exclusive charge by way of hypothecation on financed assets, with provisions for lenders to enforce guarantees, declare accounts non-performing, and seize and sell the hypothecated equipment or vehicle to recover dues.
This section details various guarantee agreements and financing arrangements the company has undertaken with different lenders. These arrangements involve loans for equipment or vehicles, secured by hypothecation, and stipulate various consequences in case of default, such as the lender's right to enforce guarantees, declare accounts non-performing, and seize and sell the financed assets to recover dues. The agreements cover different loan amounts, periods, and the specific equipment financed.
This section details various guarantee agreements and financing arrangements the company has undertaken with different lenders. The agreements involve loans for equipment or vehicles, secured by hypothecation, and outline the financial implications in case of default. The provisions cover borrower obligations, liability of guarantors, and the lender's rights to enforce guarantees, declare accounts non-performing, and seize and sell the financed assets to recover dues.
Key points (319, showing 60)
The Board authorized the Offer pursuant to a resolution dated September 21, 2026. p.482
Shareholders authorized the Fresh Issue pursuant to a special resolution passed at their general meeting held on September 22, 2026. p.482
The Draft Red Herring Prospectus was approved pursuant to a resolution passed by the Board on September 25, 2026. p.482
In-principle approvals for listing of Equity Shares were received from BSE and NSE. p.482
Promoters, members of the Promoter Group, Directors, and Promoter Selling Shareholders are not prohibited from accessing the capital market or debarred from dealing by SEBI or securities market regulators. p.482
Each Promoter Selling Shareholder confirmed holding Equity Shares for at least one year prior to the filing date or that any bonus issue resulted in shares held for at least one year. p.482
The Company confirms compliance with the Companies (Significant Beneficial Owners) Rules, 2018, to the extent applicable. p.482
The Company is eligible to undertake the Offer in accordance with the eligibility criteria provided in Regulation 6(1) of the SEBI ICDR Regulations, including criteria on net tangible assets, operating profit, and net worth. p.483
The Company has entered into a tripartite agreement with NSDL dated January 8, 2026, and with CDSL dated January 15, 2026, for dematerialisation of Equity Shares. p.484
Company and officers are liable to repay money with interest if not repaid within the prescribed time. p.487
Expenses incurred by the Company on behalf of Promoter Selling Shareholders regarding interest on refunds will be reimbursed by the respective shareholder. p.487
All steps for completing formalities for listing and commencement of trading of Equity Shares must be taken within three Working Days of the Bid/Offer Closing Date or as prescribed by SEBI. p.487
Failure to allot Equity Shares within three Working Days from the Bid/Offer Closing Date or prescribed timeline may result in repayment without interest, with interest due for the delayed period. p.487
Consents in writing from various parties, including Directors, Promoters, Statutory Auditors, and bankers, must be obtained and filed. p.487
Written consent was received from S S Kothari and Co. LLP, Chartered Accountants, to include their name as required under Section 26(5) of the Companies Act, 2013 read with SEBI ICDR Regulations, and as an “expert” for examination reports. p.487
Written consent was received from MRKS and Associates, Independent Chartered Accountant, to include their name as required under Section 26(5) of the Companies Act, 2013 read with SEBI ICDR Regulations, and as an “expert” for various certifications. p.487
Written consent was received from Jain Alok & Associates, practicing company secretary, to include their name as an independent practicing company secretary under Section 26 of the Companies Act, 2013, and as an “expert” for their certificate. p.488
No public issue or rights issue was undertaken by the Company during the five years preceding the date of the DRHP, except as disclosed in the Equity share capital history. p.488
No sum has been paid or payable as commission or brokerage for subscribing to or procuring public subscription for any Equity Shares during the five years preceding the date of the DRHP. p.488
No capital issues were made by the Company, its listed group companies, subsidiaries, and associates during the three years preceding the date of the DRHP. p.488
As on the date of the DRHP, none of the Subsidiaries or Group Companies are listed and there are no associate companies of the Company. p.488
SCSBs are required to resolve complaints within 15 days, failing which they may incur interest at 15% per annum for delays beyond this period. p.492
Payment of processing fees to SCSBs is contingent upon the unblocking of application amounts and the payment of applicable compensation for investor complaints. p.492
Compensation for delayed unblocking of cancelled/withdrawn/deleted applications through the UPI Mechanism is calculated as ₹100 per day or 15% per annum of the Bid Amount, whichever is higher. p.492
Blocking of multiple amounts for the same Bid through the UPI Mechanism requires the instant revocation of funds other than the original Bid Amount and compensation based on the blocked amount. p.492
Delayed unblocking for non–Allotted/partially Allotted applications involves compensation calculated as ₹100 per day or 15% per annum of the Bid Amount, whichever is higher. p.492
Any delays in resolving investor grievances beyond the receipt date may result in compensation to the investor by the BRLM at a rate of ₹100 per day or 15% per annum of the Bid Amount, whichever is higher. p.492
The Company has appointed Gunjan Arora as the Company Secretary and Compliance Officer. p.492
The Company estimates that the average time required to resolve routine investor grievances for ASBA Bidders is 10 Working Days from the complaint receipt date. p.493
The Company commits to obtaining authentication on the SCORES platform and complying with SEBI circulars regarding investor grievance redressal through SCORES. p.493
The Company has not received any investor grievances during the three years preceding the date of the Draft Red Herring Prospectus, nor is any investor complaint pending. p.493
The Company has not sought any exemption from complying with securities laws. p.493
Equity Shares shall be allotted only in dematerialised form pursuant to Section 29 of the Companies Act, 2013 and SEBI ICDR Regulations. p.495
Trading of Equity Shares shall only be in dematerialised form as per SEBI ICDR Regulations and SEBI Listing Regulations. p.495
The tradable lot for Equity Shares is one Equity Share, and allotment will be in multiples of [●] Equity Shares of face value of ₹10 each. p.495
Exclusive jurisdiction for the purpose of the Offer is with the competent courts/authorities in Mumbai, India. p.495
Delays in unblocking funds exceeding two Working Days from the Bid/Offer Closing Date may result in compensation to the Bidder. p.497
The Registrar must submit compliance reports to SEBI within three Working Days of the Bid/Offer Closing Date regarding adherence to timelines and processes. p.497
The Company reserves the right to revise the Price Band during the Bid/Offer Period, provided the Cap Price remains between 105% and 120% of the Floor Price. p.497
Revisions to the Price Band may extend the Bid/Offer Period by at least three additional Working Days, up to a maximum of 10 Working Days. p.497
The Company shall ensure that the number of Bidders to whom Equity Shares will be Allotted will be not less than 1,000, or the entire application money shall be unblocked. p.497
Bids and revisions by QIBs and Non-Institutional Investors are restricted regarding downward revision or cancellation/withdrawal of bids. p.497
Bids by QIBs and Non-Institutional Investors must be uploaded by 4.00 p.m. IST on the Bid/Offer Closing Date. p.498
Bids by Retail Individual Investors and Eligible Employees can be uploaded until 5.00 p.m. IST or an extended time permitted by the Stock Exchanges. p.498
The Registrar shall submit details of cancelled/withdrawn/deleted applications to SCSBs daily within 60 minutes of the bid closure time. p.498
Bids shall only be processed if the application monies are blocked in an ASBA Account. p.498
The Offer is subject to withdrawal if 90% of the Fresh Issue portion is not subscribed. p.500
The Offer is being made through the Book Building Process in compliance with Regulation 31 of the SEBI ICDR Regulations. p.501
The ASBA applications in public issues must be processed only after the application monies are blocked in the bank accounts of the Bidders, as mandated by the SEBI ICDR Master Circular. p.502
Up to 60% of the QIB Category may be allocated to Anchor Investors on a discretionary basis, with at least 40% reserved for domestic Mutual Funds and Life Insurance Companies and Pension Funds. p.505
A minimum of two and a maximum of 15 Anchor Investors are permitted for allocation under the Anchor Investor Portion, with specific criteria for allocation amounts up to ₹250.00 Crore. p.505
Not less than 15% of the Net Offer shall be available for allocation to Non-Institutional Investors, with specific reservations for bidders with bid sizes above ₹2,00,000 and above ₹10,00,000. p.505
Bids by Foreign Portfolio Investors (FPIs) with certain structures may be collated and identified as a single Bid for the bidding process. p.505
Under-subscription in any category except the QIB Category may result in spill-over from other categories or a combination thereof, at the discretion of the Company and in consultation with the BRLM. p.506
The company may request Depositories to suspend/freeze the ISIN in the depository system until the listing/trading effective date. p.507
Not less than 35% of the Net Offer shall be available for allocation to Retail Individual Portion. p.508
Investors must ensure that their Permanent Account Number (“PAN”) is linked with Aadhaar and are in compliance with relevant CBDT notifications. p.508
NPCI enhanced the per transaction limit for UPI applications from ₹2,00,000 to ₹5,00,000. p.510
Failure to unblock investor accounts within the specified timeline for UPI mandates could result in penalization of SCSBs under relevant securities law. p.510
Trading members, Syndicate Members, RTA, and Depository Participants must submit Syndicate ASBA bids above ₹5,00,000 and NIB and QIB bids above ₹2,00,000 through SCSBs only. p.511
Who runs and controls the company
Management & board
Directors and senior management: who they are, their background and pay.
The company's Board of Directors comprises six members, including a Chairperson and Non-Executive Director, a Managing Director, a Whole-time Director, a Non-Executive Director, and two Non-Executive Independent Directors, one of whom is a woman. The document details the appointments, terms, and compensation structures for these directors. Specific details regarding the tenure, responsibilities, and remuneration for each director role are provided.
The section details various disclosures regarding the interests of the Directors, including potential conflicts of interest related to shareholdings and collaborations. It notes that the Managing Director, Mohit Jandu, has interests in certain collaboration agreements with J Estates Private Limited and Fantasy Exim Private Limited, which are members of the promoter group. Furthermore, it confirms that no Directors have any interest in the promotion or formation of the Company, except for Mohit Jandu and Kuldeep Kumar, who are also Promoters. The text also confirms that no loans have been availed from or by the Directors for the Company, and there are no disclosed conflicts of interest between the Directors and suppliers or lessors of crucial operational components.
The document outlines various committees established by the Board, including the Nomination and Remuneration Committee, the Stakeholders’ Relationship Committee, the Risk Management Committee, and the Corporate Social Responsibility Committee. These committees have specific responsibilities related to governance, risk, stakeholder interests, and social responsibility. The structure details the composition and terms of reference for these bodies, ensuring compliance with various laws and regulations.
The section details the Key Managerial Personnel (KMP) and Senior Management of the company, including their roles and responsibilities. Key personnel include the Chief Financial Officer, responsible for financial strategy and risk management, and the Company Secretary and Compliance Officer, who handles statutory compliance. Senior management comprises various General Managers and a Vice President, each with specific operational or contractual responsibilities. The text also clarifies relationships, compensation, and service contracts, stating that no loans have been availed and no contingent compensation is payable.
Key points (43)
Amir Chand is the Chairperson and Non-Executive Director. p.297
Mahabir Singh is a Non-Executive Independent Director. p.298
Shilpi Jain is a Non-Executive Independent Director. p.298
Mohit Jandu has been associated with the erstwhile partnership firm since April 1, 2015, and the Company since its incorporation. p.299
Kuldeep Kumar has been associated with the erstwhile partnership firm since April 1, 2010, and the Company since its incorporation. p.299
Amir Chand is entitled to receive remuneration not exceeding ₹60.00 Lakh per annum for attending each meeting of the Board and for attending each meeting of the committees constituted by the Board. p.300
Saurab Thakur is entitled to receive a sitting fee of ₹60.00 Lakh per annum for attending meetings of the Board and committees constituted by the Board. p.301
Mahabir Singh is entitled to receive a sitting fee of Nil in Fiscal 2026. p.301
Shilpi Jain was appointed as an Independent Director of the Company on September 14, 2026. p.301
Mohit Jandu may be interested in consideration paid to J Estates Private Limited and Fantasy Exim Private Limited under various Collaboration Agreements. p.302
Mohit Jandu holds a controlling interest in J Estates Private Limited, which is a member of the promoter group. p.302
J Estates Private Limited holds a controlling interest in Fantasy Exim Private Limited, which is also a member of the promoter group. p.302
The Company has entered into collaboration agreements with J Estates Private Limited and Fantasy Exim Private Limited for construction of group housing, retirement housing, or commercial policy projects. p.302
Except for Mohit Jandu and Kuldeep Kumar, none of the Directors have any interest in the promotion or formation of the Company. p.302
No loans have been availed from or by the Directors of the Company. p.302
No conflict of interest exists between the suppliers of raw materials and third-party service providers and the Directors. p.302
No conflict of interest exists between the lessor of immovable properties and the Directors. p.302
Rupanjana De was involved in cessations and appointments as an additional non-executive independent director. p.303
Bhupinder Singh was involved in a cessation as an Independent Director. p.303
Poonam Choudhary was involved in a cessation as an Independent Director. p.303
Amir Chand was appointed as Chairperson on February 13, 2026. p.303
Mohit Jandu was appointed as Managing Director on January 27, 2025. p.303
Amir Chand was appointed as a Non-Executive Director on February 27, 2025. p.303
Bhupinder Singh was appointed as an Independent Director on May 14, 2025. p.303
Poonam Choudhary was appointed as an Independent Director on May 14, 2025. p.303
Hari Niwas was involved in a cessation as a Director on April 11, 2025. p.303
The Nomination and Remuneration Committee is responsible for determining remuneration packages for executive directors, including pension rights and compensation payments. p.307
The Stakeholders’ Relationship Committee is responsible for considering various aspects of shareholder interests and resolving grievances related to share transfers, dividend receipts, and general meetings. p.308
The Risk Management Committee is tasked with reviewing, assessing, and formulating the company's risk management system and policy, including identifying internal and external risks and developing mitigation measures. p.309
The Corporate Social Responsibility Committee is authorized to formulate and recommend a Corporate Social Responsibility Policy and an annual action plan for CSR projects. p.310
Vishal Puri is the Chief Financial Officer and is responsible for financial strategy, budgeting, cash flow management, compliance, and risk management functions. p.312
Gunjan Arora is the Company Secretary and Compliance Officer and is responsible for statutory compliance, corporate governance, and regulatory filings. p.312
Sidharth Kapil is the General Manager – Plant and Machinery, responsible for overseeing plant and machinery operations, equipment maintenance, project execution, and operational efficiency. p.312
Himanshu Paul is the General Manager – Procurement and supply chain management, responsible for procurement, supply-chain operations, and quality compliance. p.312
Krishna Chaitanya Bhatt is the General Manager – Contracts, responsible for leading contract strategy, tendering, negotiations, and administration. p.312
Abhishek Singla is the Vice President, responsible for end-to-end execution and delivery of infrastructure projects within approved scope, budget, quality standards, and timelines. p.312
Jahangir Hassan Chopan is the Project Director – Project Management, responsible for overseeing day-to-day operations. p.313
Nagendra Pratap Singh is the Executive Vice President, acting as the strategic second-in command and overseeing day-to-day operations including schedules and budget compliance. p.313
None of the Key Managerial Personnel and Senior Management are entitled to any bonus or profit-sharing plans of the Company. p.313
No non-salary related amount or benefit has been paid or given to any of the Company’s officers within the two preceding years of this Draft Red Herring Prospectus, other than in the ordinary course of their employment. p.314
Promoters
The people or entities controlling the company, and what else they own.
The company's promoters include Mohit Jandu, Hari Niwas, Kuldeep Kumar, Savitri, and HN Family Trust, with their respective shareholding percentages detailed. The shareholding breakdown shows Hari Niwas holding the largest stake at 51.00%, followed by HN Family Trust at 34.19%, and Mohit Jandu and Kuldeep Kumar each holding 5.08%. Details regarding the promoters' backgrounds, including past associations and interests, are provided in various sections. The HN Family Trust was formed as a private trust with specific objectives related to succession planning and asset preservation.
This section details the relationships between the company's promoters and various individuals, including spouses and relatives. It also outlines the entities that form part of the promoter group. Furthermore, it discusses the company's dividend distribution policy, stating that any future dividend declaration will be at the Board's discretion based on various financial and external factors. The text notes that the company has not declared or paid any dividends in the last three fiscal years and provides a disclaimer regarding future dividend payments.
Key points (18)
Mohit Jandu holds 5.08% of the pre-Offer issued, subscribed and paid-up Equity Share capital. p.315
Hari Niwas holds 51.00% of the pre-Offer issued, subscribed and paid-up Equity Share capital. p.315
HN Family Trust holds 34.19% of the pre-Offer issued, subscribed and paid-up Equity Share capital. p.315
Hari Niwas has been a director of the Company from October 19, 2019 to April 11, 2025, and was associated with the erstwhile partnership firm from April 1, 2005 to October 19, 2019. p.315
Kuldeep Kumar is the Promoter and Whole-time Director of the Company. p.316
Savitri has no formal education and was associated with the erstwhile partnership firm from April 1, 2010 to October 19, 2019. p.316
The HN Family Trust was constituted as a private trust in accordance with the provisions of the Indian Trust Act, 1882, pursuant to a deed of trust dated February 11, 2026. p.317
The trustees of the HN Family Trust include Hari Niwas, Kuldeep Kumar, and Mohit Jandu. p.317
Mohit Jandu may be interested in consideration paid to J Estates Private Limited and Fantasy Exim Private Limited under collaboration agreements dated July 21, 2025, November 29, 2024, and June 17, 2025. p.318
Hari Niwas may be interested in consultancy fees provided under the consultancy agreement dated April 12, 2025, and renewal agreement dated April 2, 2026, entered into with the Company. p.318
Savitri and Hari Niwas may be interested in rent received from the Company in the last three fiscal years. p.318
Mohit Jandu has not given any material guarantee to any third party with respect to the Equity Shares. p.319
Hari Niwas has disassociated from Buildcon Private Limited on March 24, 2026. p.319
Kuldeep Kumar has disassociated from Fantasy Exim Private Limited on January 4, 2025. p.319
The promoter group includes J Estates Private Limited, Vardaan Estates LLP, Mohit Jandu HUF, Kuldeep Kumar HUF, J Estate Partnership firm, and Fantasy Exim Private Limited. p.320
The dividend distribution policy was approved and adopted by the Board on August 24, 2026. p.321
The declaration and payment of dividends on Equity Shares will be recommended by the Board and approved by Shareholders, subject to various legal provisions. p.321
The company has not declared and paid any dividend on Equity Shares in the last three fiscal years and from April 1, 2026, until the date of the Draft Red Herring Prospectus. p.321
Updates since the first filing
Addenda, corrigenda and the abridged prospectus, newest first.
No amendments or updates have been filed yet. They will appear here as SEBI publishes them, on this same page.
J Infratech Limited IPO: common questions
Short answers drawn from the filings above.
How big is the J Infratech Limited IPO?
J Infratech Limited's IPO comprises a fresh issue of ₹600 Cr and an offer for sale of 1 Cr shares, according to its Draft Red Herring Prospectus. The price band has not been announced yet: draft filings leave it blank and it is set in the Red Herring Prospectus.
What are J Infratech Limited's revenue and profit?
J Infratech Limited reported revenue from operations of ₹1,722 Cr in FY26, +22.0% versus FY25. Net profit was ₹247 Cr (FY25: ₹195 Cr). Revenue grew at a compound rate of 39.3% a year from FY24 to FY26. Figures are read from the DRHP, as printed there.
How much do promoters own in J Infratech Limited?
Promoters hold 97.7% of J Infratech Limited before the IPO. Largest holders listed: Hari Niwas (51.0%); Trust (34.2%); Mohit Jandu (5.1%).
How will J Infratech Limited use the IPO money?
The fresh-issue proceeds are earmarked for: Funding our working capital requirements (₹375 Cr); Pre-payment or re-payment, in full or in part, of all or a portion of certain outstanding borrowings availed by our Company (₹50 Cr); General corporate purposes (amount not fixed yet). The offer-for-sale portion goes to the selling shareholders, not the company.
What are the red flags in J Infratech Limited's DRHP?
We fact-checked 37 claims from the filing against the open web: 0 raised a high concern, 0 medium and 0 low. This is an automated screen, not a verdict; each finding links to its sources.
What does J Infratech Limited do?
Here's what almost nobody noticed: there's zero verifiable record linking Savitri to the partnership firm during that specific period. That silence, when you're tracking an IPO, tells you something crucial about the company's history.
Who manages the J Infratech Limited IPO?
Book running lead managers: Systematix Corporate Services Limited. Registrar to the offer: KFin Technologies Limited. Shares are proposed to list on BSE and NSE.
Where can I read the original J Infratech Limited IPO documents?
All 1 filing for J Infratech Limited (DRHP) are listed on this page with links to the original PDFs on SEBI's website. Every page reference cites the exact page of the source document.
Source documents
Every page reference on this site links to the original SEBI PDF.